Cases / Tendering & procurement
Tendering & procurement

Check the RBQ subclass and price GST and QST in parallel

Record a Quebec subcontractor's RBQ licence with the subclass it actually carries, check that subclass covers the scope before you award, and price the job with GST and QST as two parallel lines taken on the same pre-tax base.

5 steps16 minGeneral contractorSpecialist subcontractorCost consultancy / QS practice

How it works, step by step

5 steps across the platform - what you do at each one, and why it matters.

1

Record the licence with its subclass, not just its number

Subcontractor Directory

Add the RBQ licence to the subcontractor's record with the class and subclass it carries and the date it expires, and file the certificate itself beside it rather than a note saying it was seen.

Why: A register that says only that a firm is licensed has answered the easy half of the question. The subclass is what states the work the licence actually permits, and without it on the record nobody can tell later whether the right question was ever asked.

InLicence certificate from the subcontractorScope of the packageOutLicence on record with its subclassExpiry date on file
2

Read the subclass against the scope before you award

Subcontractor Directory

Before the award, read the subclass on the licence against the work the package actually contains. Where the scope crosses into work the subclass does not cover, either split the package or ask the firm for the licence that covers it, and record which you did.

Why: This is the check that a process built for another market does not make: it confirms a licence exists and stops there. In Quebec the licence usually exists and is the wrong one more often than it is missing, and the party who finds out is the owner of the project, at the worst possible moment.

InLicence subclass on recordWork the package containsOutScope covered by the licence heldPackage split where it is not
3

Build the bill as a Quebec estimator would write it

BOQ

Write the item descriptions in French, keep the quantities metric and the prices in Canadian dollars at a Montreal level, and structure the bill by the divisions your client and their consultants already read.

Why: The client, the architect and the engineer read the bill in French and check it against documents written in French. A bill that arrives translated back out of another language reads as a bid prepared somewhere else, and the first thing that gets questioned after that is the price.

InMeasured quantitiesMontreal cost ratesOutBill written in FrenchMetric quantities priced in CAD
4

Put the two taxes side by side, not one on top of the other

Markups

Add GST at 5 percent and QST at 9.975 percent as two separate lines, both taken on the same pre-tax subtotal, and show the base each one was computed on rather than only the combined figure.

Why: The two taxes are parallel, not stacked, and 14.975 percent is the sum of two rates on one base rather than one rate applied to the other's result. Compounding them adds half a percent of the contract to your price, which loses a competitive bid, or leaves it out of a cost plan, which loses money on the job. Showing the base is what lets the client verify it in a glance instead of a phone call.

InPre-tax subtotalCurrent GST and QST ratesOutTwo tax lines on one baseThe base each was taken on
5

Read the tax and the licences back before the bid goes out

Reports

Before the bid leaves, read back the two things this case turns on: the pre-tax total with the two tax lines and the base each was taken on, and which firms hold a licence whose subclass covers the scope they were priced for.

Why: A Quebec client checks both of those first, and both are far cheaper to correct while the bid is still yours. A tax computed the way Revenu Quebec computes it, and a licence that covers the work it was priced for, are what turn a week of evaluation correspondence into no correspondence at all.

InPriced bill and tax linesSubcontractor licence detailsOutA tax build-up that reconcilesLicensed scopes confirmed covered
Modules

Modules in this playbook

4 / 190 platform modules

The market this case is written for

Canada

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

More in Tendering & procurement

Tendering & procurement

Run a tender from a BOQ

Take a priced bill of quantities out to market: package it, invite the subcontractors, leve…

5 steps12 minOpen
Tendering & procurement

Procure materials from the BOQ

Buy the quantities you already priced: raise a requisition off the bill, place the order wi…

4 steps10 minOpen
Tendering & procurement

Compare bids and award

Take a folder of returned tenders that never quite match, strip them back to the same scope…

3 steps12 minOpen