Memeriksa subkelas RBQ dan menetapkan harga GST serta QST secara paralel

Catat lisensi RBQ subkontraktor Quebec dengan subkelas yang benar-benar dimilikinya, periksa apakah subkelas itu mencakup lingkup sebelum Anda memberikan pekerjaan, dan tetapkan harga pekerjaan dengan GST dan QST sebagai dua baris paralel yang dihitung dari dasar pra-pajak yang sama.

5 langkah16 mntKontraktor umumSubkontraktor spesialisKonsultansi biaya / QS

Cara kerjanya, langkah demi langkah

5 langkah di seluruh platform - apa yang Anda lakukan di setiap langkah dan mengapa itu penting.

1

Record the licence with its subclass, not just its number

Direktori Subkontraktor

Add the RBQ licence to the subcontractor's record with the class and subclass it carries and the date it expires, and file the certificate itself beside it rather than a note saying it was seen.

Mengapa: A register that says only that a firm is licensed has answered the easy half of the question. The subclass is what states the work the licence actually permits, and without it on the record nobody can tell later whether the right question was ever asked.

MasukanLicence certificate from the subcontractorScope of the packageHasilLicence on record with its subclassExpiry date on file
2

Read the subclass against the scope before you award

Direktori Subkontraktor

Before the award, read the subclass on the licence against the work the package actually contains. Where the scope crosses into work the subclass does not cover, either split the package or ask the firm for the licence that covers it, and record which you did.

Mengapa: This is the check that a process built for another market does not make: it confirms a licence exists and stops there. In Quebec the licence usually exists and is the wrong one more often than it is missing, and the party who finds out is the owner of the project, at the worst possible moment.

MasukanLicence subclass on recordWork the package containsHasilScope covered by the licence heldPackage split where it is not
3

Build the bill as a Quebec estimator would write it

Daftar Kuantitas

Write the item descriptions in French, keep the quantities metric and the prices in Canadian dollars at a Montreal level, and structure the bill by the divisions your client and their consultants already read.

Mengapa: The client, the architect and the engineer read the bill in French and check it against documents written in French. A bill that arrives translated back out of another language reads as a bid prepared somewhere else, and the first thing that gets questioned after that is the price.

MasukanMeasured quantitiesMontreal cost ratesHasilBill written in FrenchMetric quantities priced in CAD
4

Put the two taxes side by side, not one on top of the other

Markup

Add GST at 5 percent and QST at 9.975 percent as two separate lines, both taken on the same pre-tax subtotal, and show the base each one was computed on rather than only the combined figure.

Mengapa: The two taxes are parallel, not stacked, and 14.975 percent is the sum of two rates on one base rather than one rate applied to the other's result. Compounding them adds half a percent of the contract to your price, which loses a competitive bid, or leaves it out of a cost plan, which loses money on the job. Showing the base is what lets the client verify it in a glance instead of a phone call.

MasukanPre-tax subtotalCurrent GST and QST ratesHasilTwo tax lines on one baseThe base each was taken on
5

Read the tax and the licences back before the bid goes out

Laporan

Before the bid leaves, read back the two things this case turns on: the pre-tax total with the two tax lines and the base each was taken on, and which firms hold a licence whose subclass covers the scope they were priced for.

Mengapa: A Quebec client checks both of those first, and both are far cheaper to correct while the bid is still yours. A tax computed the way Revenu Quebec computes it, and a licence that covers the work it was priced for, are what turn a week of evaluation correspondence into no correspondence at all.

MasukanPriced bill and tax linesSubcontractor licence detailsHasilA tax build-up that reconcilesLicensed scopes confirmed covered
Modul

Modul dalam playbook ini

4 / 190 modul platform

The market this case is written for

Kanada

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Lainnya di Tender dan pengadaan

Tender dan pengadaan

Run a tender from a BOQ

Take a priced bill of quantities out to market: package it, invite the subcontractors, leve…

5 langkah12 mntBuka
Tender dan pengadaan

Procure materials from the BOQ

Buy the quantities you already priced: raise a requisition off the bill, place the order wi…

4 langkah10 mntBuka
Tender dan pengadaan

Compare bids and award

Take a folder of returned tenders that never quite match, strip them back to the same scope…

3 langkah12 mntBuka