Případy / Předání a životní cyklus
Předání a životní cyklus

Mängel, Abnahme a hodiny Verjährung

Zaznamenejte každý Mangel s fotografií a umístěním, vyčistěte seznam před Abnahme, podepište protokol, který přesně uvádí, co bylo vyhrazeno, a sledujte vady podle promlčecí lhůty, kterou vám smlouva skutečně dává.

6 kroků11 minGenerální dodavatelProjektová / stavební manažerská firmaDeveloper / klient

Jak to funguje, krok za krokem

6 kroků napříč platformou - co na každém uděláte a proč na tom záleží.

1

Walk the building and log every Mangel

Seznam vad

Walk the building trade by trade well before the acceptance date and put every defect straight into the list: what is wrong, the room or axis it sits in, a photo, and the trade that owns the fix.

Proč: A defect written on a slip of paper and typed up three weeks later is a defect the trade disputes. Location plus photo, captured while you are standing in front of it, is what turns a complaint into something enforceable.

VstupPre-acceptance walkTrades on siteVýstupLogged MaengelPhoto and location
2

Drive the list to zero or to agreed exceptions

Kontroly

Re-inspect every item the trade reports as done, close the ones that genuinely pass and reopen the ones that do not, and mark the few that will stay open as exceptions both sides have agreed to carry into the protocol.

Proč: The acceptance appointment is the worst possible place to discover an open list. Every item closed and proven beforehand is one that cannot be reserved against you, held against your payment, or used to refuse acceptance outright.

VstupOpen MaengelReported fixesVýstupVerified closuresAgreed exceptions
3

Hold the formal Abnahme and write the protocol

Předání a uzavření

Run the acceptance walk with the client and record the Abnahmeprotokoll: the date, who was present, what was accepted, which defects are reserved, and any contract penalty the client wants to keep. Both sides sign it.

Proč: This one document decides more than any other on the project: risk passes, the final payment falls due, the burden of proof turns to the client, and the Verjaehrung starts on its date. A defect not reserved in it, and a contract penalty not reserved with it, is one nobody can raise afterwards.

VstupCleared Maengel listAcceptance appointmentVýstupSigned AbnahmeprotokollReserved defects
4

Read the limitation period off the contract

Smlouvy

Open the contract, establish whether VOB/B was validly agreed or the job runs as a plain BGB Werkvertrag, and record the limitation period that follows: four years for building works under VOB/B, five under the BGB, counted from the Abnahme date in the protocol.

Proč: The two regimes are a full year apart, and assuming the wrong one either hands the client a year you never owed or writes off a claim that was still alive. Reading it off the contract once, at the Abnahme, is what makes every deadline after it trustworthy.

VstupSigned contractAbnahme dateVýstupContract regimeVerjaehrungsfrist set
5

Track the defects through the liability period

Záruky a odpovědnost za vady

Register the reserved defects and everything reported after handover against the party obliged to fix it, each with the warranty that covers it and the date its period runs out.

Proč: A defect phoned in to a caretaker and written into nobody's list is a defect the owner quietly ends up paying to fix. One register is what keeps every claim attached to the party that owes it for as long as the period runs.

VstupReserved defectsDefects reported laterVýstupTracked claimsPeriod end date
6

Send the Maengelruege while the period is open

Termíny

Work the deadline register: the day each limitation period ends, the date a notified defect must be remedied by, and the counter-deadlines you set the contractor. Issue the Maengelruege in writing, with a deadline to put it right.

Proč: A claim raised one day after the period has run out is worth nothing, however well it was documented. A written notice sent while the period is still open is what preserves the claim, and the remedy deadline you set with it is what turns it into work on site rather than correspondence.

VstupLimitation end datesOpen defect claimsVýstupMaengelruege sentRemedy deadline set
Moduly

Moduly v tomto playbooku

6 / 190 modulů platformy

The market this case is written for

Německo

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • DIN 276
  • GAEB XML
  • VOB/B

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Více v kategorii Předání a životní cyklus

Předání a životní cyklus

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 kroků14 minOtevřít
Předání a životní cyklus

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3 kroků12 minOtevřít
Předání a životní cyklus

Run a handover acceptance inspection

Walk the finished works with the client, record what passes and what does not against the a…

3 kroků11 minOtevřít