Mängel, Abnahme e l'orologio della Verjährung

Registra ogni difetto (Mangel) con foto e posizione, azzera la lista prima dell'Abnahme, firma un verbale che dica esattamente cosa è stato riservato, e tieni traccia dei difetti sul termine di prescrizione (Verjährung) che il contratto ti dà davvero.

6 passaggi11 minImpresa generaleStudio di gestione progetti / cantieriSviluppatore / committente

Come funziona, passo dopo passo

6 passi attraverso la piattaforma - cosa fare a ciascuno e perché conta.

1

Walk the building and log every Mangel

Lista Difetti

Walk the building trade by trade well before the acceptance date and put every defect straight into the list: what is wrong, the room or axis it sits in, a photo, and the trade that owns the fix.

Schermata, passaggio 1: Walk the building and log every Mangel (Lista Difetti, Mängel, Abnahme e l'orologio della Verjährung)
Lista Difetti: Walk the building and log every Mangel

Perché: A defect written on a slip of paper and typed up three weeks later is a defect the trade disputes. Location plus photo, captured while you are standing in front of it, is what turns a complaint into something enforceable.

In entrataPre-acceptance walkTrades on siteIn uscitaLogged MaengelPhoto and location
2

Drive the list to zero or to agreed exceptions

Ispezioni

Re-inspect every item the trade reports as done, close the ones that genuinely pass and reopen the ones that do not, and mark the few that will stay open as exceptions both sides have agreed to carry into the protocol.

Schermata, passaggio 2: Drive the list to zero or to agreed exceptions (Ispezioni, Mängel, Abnahme e l'orologio della Verjährung)
Ispezioni: Drive the list to zero or to agreed exceptions

Perché: The acceptance appointment is the worst possible place to discover an open list. Every item closed and proven beforehand is one that cannot be reserved against you, held against your payment, or used to refuse acceptance outright.

In entrataOpen MaengelReported fixesIn uscitaVerified closuresAgreed exceptions
3

Hold the formal Abnahme and write the protocol

Consegna e chiusura

Run the acceptance walk with the client and record the Abnahmeprotokoll: the date, who was present, what was accepted, which defects are reserved, and any contract penalty the client wants to keep. Both sides sign it.

Schermata, passaggio 3: Hold the formal Abnahme and write the protocol (Consegna e chiusura, Mängel, Abnahme e l'orologio della Verjährung)
Consegna e chiusura: Hold the formal Abnahme and write the protocol

Perché: This one document decides more than any other on the project: risk passes, the final payment falls due, the burden of proof turns to the client, and the Verjaehrung starts on its date. A defect not reserved in it, and a contract penalty not reserved with it, is one nobody can raise afterwards.

In entrataCleared Maengel listAcceptance appointmentIn uscitaSigned AbnahmeprotokollReserved defects
4

Read the limitation period off the contract

Contratti

Open the contract, establish whether VOB/B was validly agreed or the job runs as a plain BGB Werkvertrag, and record the limitation period that follows: four years for building works under VOB/B, five under the BGB, counted from the Abnahme date in the protocol.

Schermata, passaggio 4: Read the limitation period off the contract (Contratti, Mängel, Abnahme e l'orologio della Verjährung)
Contratti: Read the limitation period off the contract

Perché: The two regimes are a full year apart, and assuming the wrong one either hands the client a year you never owed or writes off a claim that was still alive. Reading it off the contract once, at the Abnahme, is what makes every deadline after it trustworthy.

In entrataSigned contractAbnahme dateIn uscitaContract regimeVerjaehrungsfrist set
5

Track the defects through the liability period

Garanzie e responsabilità per difetti

Register the reserved defects and everything reported after handover against the party obliged to fix it, each with the warranty that covers it and the date its period runs out.

Schermata, passaggio 5: Track the defects through the liability period (Garanzie e responsabilità per difetti, Mängel, Abnahme e l'orologio della Verjährung)
Garanzie e responsabilità per difetti: Track the defects through the liability period

Perché: A defect phoned in to a caretaker and written into nobody's list is a defect the owner quietly ends up paying to fix. One register is what keeps every claim attached to the party that owes it for as long as the period runs.

In entrataReserved defectsDefects reported laterIn uscitaTracked claimsPeriod end date
6

Send the Maengelruege while the period is open

Scadenze

Work the deadline register: the day each limitation period ends, the date a notified defect must be remedied by, and the counter-deadlines you set the contractor. Issue the Maengelruege in writing, with a deadline to put it right.

Perché: A claim raised one day after the period has run out is worth nothing, however well it was documented. A written notice sent while the period is still open is what preserves the claim, and the remedy deadline you set with it is what turns it into work on site rather than correspondence.

In entrataLimitation end datesOpen defect claimsIn uscitaMaengelruege sentRemedy deadline set
Moduli

Moduli di questo playbook

6 / 190 moduli della piattaforma

The market this case is written for

Germania

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • DIN 276
  • GAEB XML
  • VOB/B

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Altro in Consegna e ciclo di vita

Consegna e ciclo di vita

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 passaggi14 minApri
Consegna e ciclo di vita

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3 passaggi12 minApri