Casos / Entrega e ciclo de vida
Entrega e ciclo de vida

Maengel, Abnahme and the Verjaehrung clock

Log every Mangel with photo and location, clear the list before the Abnahme, sign a protocol that says exactly what was reserved, and track the defects on the limitation period the contract really gives you.

6 etapas11 minEmpreiteiro geralGabinete de gestão de projetos / obrasPromotor / cliente

Como funciona, passo a passo

6 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Walk the building and log every Mangel

Lista de Pendências

Walk the building trade by trade well before the acceptance date and put every defect straight into the list: what is wrong, the room or axis it sits in, a photo, and the trade that owns the fix.

Por quê: A defect written on a slip of paper and typed up three weeks later is a defect the trade disputes. Location plus photo, captured while you are standing in front of it, is what turns a complaint into something enforceable.

EntradaPre-acceptance walkTrades on siteResultadoLogged MaengelPhoto and location
2

Drive the list to zero or to agreed exceptions

Inspeções

Re-inspect every item the trade reports as done, close the ones that genuinely pass and reopen the ones that do not, and mark the few that will stay open as exceptions both sides have agreed to carry into the protocol.

Por quê: The acceptance appointment is the worst possible place to discover an open list. Every item closed and proven beforehand is one that cannot be reserved against you, held against your payment, or used to refuse acceptance outright.

EntradaOpen MaengelReported fixesResultadoVerified closuresAgreed exceptions
3

Hold the formal Abnahme and write the protocol

Entrega e Encerramento

Run the acceptance walk with the client and record the Abnahmeprotokoll: the date, who was present, what was accepted, which defects are reserved, and any contract penalty the client wants to keep. Both sides sign it.

Por quê: This one document decides more than any other on the project: risk passes, the final payment falls due, the burden of proof turns to the client, and the Verjaehrung starts on its date. A defect not reserved in it, and a contract penalty not reserved with it, is one nobody can raise afterwards.

EntradaCleared Maengel listAcceptance appointmentResultadoSigned AbnahmeprotokollReserved defects
4

Read the limitation period off the contract

Contratos

Open the contract, establish whether VOB/B was validly agreed or the job runs as a plain BGB Werkvertrag, and record the limitation period that follows: four years for building works under VOB/B, five under the BGB, counted from the Abnahme date in the protocol.

Por quê: The two regimes are a full year apart, and assuming the wrong one either hands the client a year you never owed or writes off a claim that was still alive. Reading it off the contract once, at the Abnahme, is what makes every deadline after it trustworthy.

EntradaSigned contractAbnahme dateResultadoContract regimeVerjaehrungsfrist set
5

Track the defects through the liability period

Garantias e responsabilidade por defeitos

Register the reserved defects and everything reported after handover against the party obliged to fix it, each with the warranty that covers it and the date its period runs out.

Por quê: A defect phoned in to a caretaker and written into nobody's list is a defect the owner quietly ends up paying to fix. One register is what keeps every claim attached to the party that owes it for as long as the period runs.

EntradaReserved defectsDefects reported laterResultadoTracked claimsPeriod end date
6

Send the Maengelruege while the period is open

Prazos

Work the deadline register: the day each limitation period ends, the date a notified defect must be remedied by, and the counter-deadlines you set the contractor. Issue the Maengelruege in writing, with a deadline to put it right.

Por quê: A claim raised one day after the period has run out is worth nothing, however well it was documented. A written notice sent while the period is still open is what preserves the claim, and the remedy deadline you set with it is what turns it into work on site rather than correspondence.

EntradaLimitation end datesOpen defect claimsResultadoMaengelruege sentRemedy deadline set
Módulos

Módulos deste playbook

6 / 184 módulos da plataforma

Mais em Entrega e ciclo de vida

Entrega e ciclo de vida

Entregar e encerrar a obra

Termine a obra de forma limpa: leve a lista de pendências a zero, confirme que todas as insp…

5 etapas14 minAbrir
Entrega e ciclo de vida

Entrega as-built e de O&M

Reúna o registo as-built, comprove que o dossier de qualidade não tem lacunas, e emita um pa…

3 etapas12 minAbrir