Byg en Nachtrag på bevis, ikke på argumentation

Jorden er anderledes, tegningen ændrede sig, bygherren bestilte ekstra. Registrer den ændrede tilstand på pladsen den dag, den viser sig, prissæt den mod kontraktgrundlaget, og følg Nachtrag fra angemeldet til beauftragt.

7 trin13 minHovedentreprenørFagentreprenørOmkostnings- / mængderådgivning

Sådan fungerer det, trin for trin

7 trin gennem platformen - hvad du gør i hvert, og hvorfor det betyder noget.

1

Write the changed condition into the diary

Byggedagbog

On the day the ground turns out different, the revised drawing lands or the client orders something extra, write it into the site diary: what was found and where, which crews and plant were standing there, the weather, and the instruction or drawing revision behind it.

Skærmbillede, trin 1: Write the changed condition into the diary (Byggedagbog, Byg en Nachtrag på bevis, ikke på argumentation)
Byggedagbog: Write the changed condition into the diary

Hvorfor: A diary entry is dated by the day it was written, not by the day the argument starts. That is the whole difference between a Nachtrag the other side reads and one they take apart line by line.

InputChanged site conditionRevised drawingClient instructionResultatDated diary entryWho was on site
2

Photograph it while it is still open

Projektfotos

Upload the photographs the same day: the open trench, the layer that was not in the soil report, the obstruction nobody drew. The gallery reads the capture date and GPS position off each file, so every shot carries its own date and place without you typing one.

Hvorfor: Once the excavation is backfilled nobody can photograph it again. A dated, located photograph is the cheapest evidence on the project and the one thing that settles whether the ground really was different.

InputSite photographsDiary entry it belongs toResultatDated geotagged photosRecord of the condition
3

Announce the Nachtrag before you build it

Ekstraarbejder

Raise the notice in the variations register as soon as the change is spotted: name the changed or additional work under paragraph 2 VOB/B, name the recipient, and set the date you expect an answer by. The notice goes in before the work is carried out.

Skærmbillede, trin 3: Announce the Nachtrag before you build it (Ekstraarbejder, Byg en Nachtrag på bevis, ikke på argumentation)
Ekstraarbejder: Announce the Nachtrag before you build it

Hvorfor: Announcing first and building second is what keeps the entitlement alive. A Nachtrag announced after the work is finished invites the reply that nobody ordered it, however good the site records are.

InputDiary entry and photosInstruction or revisionResultatNachtrag angemeldetRecipient and response date
4

Book the Stundenlohn hours and get them signed

Felttid

Where the work runs as Stundenlohnarbeiten, book the labour and plant hours against the change and flag the lines as daywork rather than measured work, then get the Stundenlohnzettel countersigned by the site supervision inside the period the contract allows.

Hvorfor: Daywork is recovered against the Nachtrag and measured work against the bill; mix them and you lose both. An unsigned Stundenlohnzettel handed over weeks late is the easiest item on any Nachtrag to strike out.

InputLabour and plant hoursCost code for the changeAnnounced NachtragResultatCountersigned StundenlohnzettelApproved daywork hours
5

Price it against the contract basis

Tilbudsliste

Derive the new position from the nearest position in the contract bill rather than inventing a fresh price, carry the same cost elements the original calculation was built on, and measure the omitted work as carefully as the added.

Skærmbillede, trin 5: Price it against the contract basis (Tilbudsliste, Byg en Nachtrag på bevis, ikke på argumentation)
Tilbudsliste: Price it against the contract basis

Hvorfor: A Nachtrag built on the original calculation can be checked in an afternoon. One built on a market rate that has nothing to do with the contract turns the whole negotiation into a fight about the price basis instead of the work.

InputContract positions and ratesAdded and omitted workResultatPriced Nachtrag positionTraceable price basis
6

Submit it and follow it to beauftragt

Ekstraarbejder

Turn the announced change into a priced request with its cost and time impact set out, submit it against the notice it answers, and follow it through review to an agreed order that carries the figure into the contract final account.

Skærmbillede, trin 6: Submit it and follow it to beauftragt (Ekstraarbejder, Byg en Nachtrag på bevis, ikke på argumentation)
Ekstraarbejder: Submit it and follow it to beauftragt

Hvorfor: Priced but never formally submitted is work done for free. Tracking every open Nachtrag from angemeldet to beauftragt in one register is what stops a folder of changes agreed in principle reaching the final account unbooked.

InputPriced NachtragThe notice it answersResultatSubmitted Nachtrag offerNachtrag beauftragt
7

Check it would survive a challenge

Kravbeviser

Before the Nachtrag is contested, read its provability score: whether the notice went out in time, whether the other side acknowledged it, whether it ties to a governing instruction and a dated contemporaneous record. Work the weakest gap first, then assemble the evidence thread into one exportable pack.

Skærmbillede, trin 7: Check it would survive a challenge (Kravbeviser, Byg en Nachtrag på bevis, ikke på argumentation)
Kravbeviser: Check it would survive a challenge

Hvorfor: This is the step that decides whether a Nachtrag is paid or talked down. Finding the missing acknowledgement while the site is still open costs one email; finding it at the final account costs the whole item.

InputSubmitted NachtragDiary, photos, signed sheetsResultatProvability scoreExportable evidence pack
Moduler

Moduler i denne playbook

6 / 190 platformmoduler

The market this case is written for

Tyskland

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • DIN 276
  • GAEB XML
  • VOB/B

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Mere inden for Kommercielt og kontrakter

Kommercielt og kontrakter

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 trin11 minÅbn