Build a Nachtrag on evidence, not argument

The ground is different, the drawing changed, the client ordered extra. Capture the changed condition on site the day it appears, price it against the contract basis, and follow the Nachtrag from angemeldet through to beauftragt.

7 个步骤13 分钟总承包商专业分包商造价咨询 / 工料测量顾问

运作方式,逐步说明

贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。

1

Write the changed condition into the diary

施工日志

On the day the ground turns out different, the revised drawing lands or the client orders something extra, write it into the site diary: what was found and where, which crews and plant were standing there, the weather, and the instruction or drawing revision behind it.

原因: A diary entry is dated by the day it was written, not by the day the argument starts. That is the whole difference between a Nachtrag the other side reads and one they take apart line by line.

输入Changed site conditionRevised drawingClient instruction成果Dated diary entryWho was on site
2

Photograph it while it is still open

项目照片

Upload the photographs the same day: the open trench, the layer that was not in the soil report, the obstruction nobody drew. The gallery reads the capture date and GPS position off each file, so every shot carries its own date and place without you typing one.

原因: Once the excavation is backfilled nobody can photograph it again. A dated, located photograph is the cheapest evidence on the project and the one thing that settles whether the ground really was different.

输入Site photographsDiary entry it belongs to成果Dated geotagged photosRecord of the condition
3

Announce the Nachtrag before you build it

变更增项

Raise the notice in the variations register as soon as the change is spotted: name the changed or additional work under paragraph 2 VOB/B, name the recipient, and set the date you expect an answer by. The notice goes in before the work is carried out.

原因: Announcing first and building second is what keeps the entitlement alive. A Nachtrag announced after the work is finished invites the reply that nobody ordered it, however good the site records are.

输入Diary entry and photosInstruction or revision成果Nachtrag angemeldetRecipient and response date
4

Book the Stundenlohn hours and get them signed

现场工时

Where the work runs as Stundenlohnarbeiten, book the labour and plant hours against the change and flag the lines as daywork rather than measured work, then get the Stundenlohnzettel countersigned by the site supervision inside the period the contract allows.

原因: Daywork is recovered against the Nachtrag and measured work against the bill; mix them and you lose both. An unsigned Stundenlohnzettel handed over weeks late is the easiest item on any Nachtrag to strike out.

输入Labour and plant hoursCost code for the changeAnnounced Nachtrag成果Countersigned StundenlohnzettelApproved daywork hours
5

Price it against the contract basis

工程量清单

Derive the new position from the nearest position in the contract bill rather than inventing a fresh price, carry the same cost elements the original calculation was built on, and measure the omitted work as carefully as the added.

原因: A Nachtrag built on the original calculation can be checked in an afternoon. One built on a market rate that has nothing to do with the contract turns the whole negotiation into a fight about the price basis instead of the work.

输入Contract positions and ratesAdded and omitted work成果Priced Nachtrag positionTraceable price basis
6

Submit it and follow it to beauftragt

变更增项

Turn the announced change into a priced request with its cost and time impact set out, submit it against the notice it answers, and follow it through review to an agreed order that carries the figure into the contract final account.

原因: Priced but never formally submitted is work done for free. Tracking every open Nachtrag from angemeldet to beauftragt in one register is what stops a folder of changes agreed in principle reaching the final account unbooked.

输入Priced NachtragThe notice it answers成果Submitted Nachtrag offerNachtrag beauftragt
7

Check it would survive a challenge

索赔证据

Before the Nachtrag is contested, read its provability score: whether the notice went out in time, whether the other side acknowledged it, whether it ties to a governing instruction and a dated contemporaneous record. Work the weakest gap first, then assemble the evidence thread into one exportable pack.

原因: This is the step that decides whether a Nachtrag is paid or talked down. Finding the missing acknowledgement while the site is still open costs one email; finding it at the final account costs the whole item.

输入Submitted NachtragDiary, photos, signed sheets成果Provability scoreExportable evidence pack
模块

此方案使用的模块

184 个平台模块中的 6

更多 商务与合同 案例

商务与合同

把变更转化为已付款的变更单

在范围变更还新鲜时就记录下来,依据你已约定的单价将其作为合同变更报价,并在下一期进度付款申请中计入,使额外工作能够获得补偿,而不是被悄悄吸收。

3 个步骤11 分钟打开
商务与合同

管理分包工程

将某工种分包给分包商,以带付款计划表和保留金条款的分包合同确定下来,再按实际完成的工作逐期支付款项。

3 个步骤11 分钟打开
商务与合同

付款申请与对账

按合同对本期已完成工作进行估值,附上依据提出申请,并将已核证的金额与账户实际到账的金额进行对账。

3 个步骤12 分钟打开