Build a Nachtrag on evidence, not argument

The ground is different, the drawing changed, the client ordered extra. Capture the changed condition on site the day it appears, price it against the contract basis, and follow the Nachtrag from angemeldet through to beauftragt.

7 pasos13 minContratista generalSubcontratista especializadoConsultoría de costos / QS

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué haces en cada uno y por qué importa.

1

Write the changed condition into the diary

Diario de obra

On the day the ground turns out different, the revised drawing lands or the client orders something extra, write it into the site diary: what was found and where, which crews and plant were standing there, the weather, and the instruction or drawing revision behind it.

Captura de pantalla, paso 1: Write the changed condition into the diary (Diario de obra, Build a Nachtrag on evidence, not argument)
Diario de obra: Write the changed condition into the diary

Por que: A diary entry is dated by the day it was written, not by the day the argument starts. That is the whole difference between a Nachtrag the other side reads and one they take apart line by line.

EntradaChanged site conditionRevised drawingClient instructionResultadoDated diary entryWho was on site
2

Photograph it while it is still open

Fotos del Proyecto

Upload the photographs the same day: the open trench, the layer that was not in the soil report, the obstruction nobody drew. The gallery reads the capture date and GPS position off each file, so every shot carries its own date and place without you typing one.

Por que: Once the excavation is backfilled nobody can photograph it again. A dated, located photograph is the cheapest evidence on the project and the one thing that settles whether the ground really was different.

EntradaSite photographsDiary entry it belongs toResultadoDated geotagged photosRecord of the condition
3

Announce the Nachtrag before you build it

Modificaciones

Raise the notice in the variations register as soon as the change is spotted: name the changed or additional work under paragraph 2 VOB/B, name the recipient, and set the date you expect an answer by. The notice goes in before the work is carried out.

Captura de pantalla, paso 3: Announce the Nachtrag before you build it (Modificaciones, Build a Nachtrag on evidence, not argument)
Modificaciones: Announce the Nachtrag before you build it

Por que: Announcing first and building second is what keeps the entitlement alive. A Nachtrag announced after the work is finished invites the reply that nobody ordered it, however good the site records are.

EntradaDiary entry and photosInstruction or revisionResultadoNachtrag angemeldetRecipient and response date
4

Book the Stundenlohn hours and get them signed

Tiempo de obra

Where the work runs as Stundenlohnarbeiten, book the labour and plant hours against the change and flag the lines as daywork rather than measured work, then get the Stundenlohnzettel countersigned by the site supervision inside the period the contract allows.

Por que: Daywork is recovered against the Nachtrag and measured work against the bill; mix them and you lose both. An unsigned Stundenlohnzettel handed over weeks late is the easiest item on any Nachtrag to strike out.

EntradaLabour and plant hoursCost code for the changeAnnounced NachtragResultadoCountersigned StundenlohnzettelApproved daywork hours
5

Price it against the contract basis

Presupuesto

Derive the new position from the nearest position in the contract bill rather than inventing a fresh price, carry the same cost elements the original calculation was built on, and measure the omitted work as carefully as the added.

Captura de pantalla, paso 5: Price it against the contract basis (Presupuesto, Build a Nachtrag on evidence, not argument)
Presupuesto: Price it against the contract basis

Por que: A Nachtrag built on the original calculation can be checked in an afternoon. One built on a market rate that has nothing to do with the contract turns the whole negotiation into a fight about the price basis instead of the work.

EntradaContract positions and ratesAdded and omitted workResultadoPriced Nachtrag positionTraceable price basis
6

Submit it and follow it to beauftragt

Modificaciones

Turn the announced change into a priced request with its cost and time impact set out, submit it against the notice it answers, and follow it through review to an agreed order that carries the figure into the contract final account.

Captura de pantalla, paso 6: Submit it and follow it to beauftragt (Modificaciones, Build a Nachtrag on evidence, not argument)
Modificaciones: Submit it and follow it to beauftragt

Por que: Priced but never formally submitted is work done for free. Tracking every open Nachtrag from angemeldet to beauftragt in one register is what stops a folder of changes agreed in principle reaching the final account unbooked.

EntradaPriced NachtragThe notice it answersResultadoSubmitted Nachtrag offerNachtrag beauftragt
7

Check it would survive a challenge

Evidencia de reclamaciones

Before the Nachtrag is contested, read its provability score: whether the notice went out in time, whether the other side acknowledged it, whether it ties to a governing instruction and a dated contemporaneous record. Work the weakest gap first, then assemble the evidence thread into one exportable pack.

Captura de pantalla, paso 7: Check it would survive a challenge (Evidencia de reclamaciones, Build a Nachtrag on evidence, not argument)
Evidencia de reclamaciones: Check it would survive a challenge

Por que: This is the step that decides whether a Nachtrag is paid or talked down. Finding the missing acknowledgement while the site is still open costs one email; finding it at the final account costs the whole item.

EntradaSubmitted NachtragDiary, photos, signed sheetsResultadoProvability scoreExportable evidence pack
Módulos

Módulos de este playbook

6 / 190 módulos de la plataforma

The market this case is written for

Alemania

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • DIN 276
  • GAEB XML
  • VOB/B

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.