سناریوها / بازرگانی و قراردادها
بازرگانی و قراردادها

ثبت تغییر تحت یک قرارداد از خانواده CCDC

درون بازه‌ای که قرارداد اجازه می‌دهد رویداد را اطلاع دهید، تغییر را در برابر بندی که تحت آن مطرح می‌شود مطرح کنید، آن را با یکی از مسیرهایی که قرارداد نام می‌برد ارزش‌گذاری کنید و بگویید کدام، و قیمت قرارداد را به‌عنوان یک عدد مشتق‌شده با دلیلی برای هر حرکت نگه دارید.

5 مرحله18 دقیقهپیمانکار عمومیدفتر مدیریت پروژه / ساختمشاوره هزینه / QS

چگونه کار می‌کند، گام به گام

5 گام در سراسر پلتفرم - کاری که در هر گام انجام می‌دهید و چرا اهمیت دارد.

1

Give the notice before you price anything

مکاتبات

Send written notice of the event from the correspondence register on the day it is found, describing what was found and where, and record the date it was given and who received it. Count the period the contract allows in working days against your own site calendar and put that date on the record beside the notice.

چرا: The general conditions give a concealed condition, a delay and a claim each their own period counted from the event or from its discovery, and a notice given late can lose an entitlement that would otherwise have been paid in full. Notice first and price second is the order that survives, because the price can be argued and the missed notice cannot.

ورودیThe site event and the day it was foundThe notice period the contract allowsخروجیNotice given and datedThe day the period runs out
2

Raise it against the clause it is raised under

تغییرات قرارداد

Open the change, name the contract and the general condition it is raised under in its reference, and attach the notice, the photographs and the survey that establish the condition you found.

چرا: A change carrying its clause reference is a change the consultant can assess without asking what it is for, which is most of the delay in getting one approved. Six months later that reference is also the difference between an approved change and an argument about whether it was ever properly raised.

ورودیThe notice as givenPhotographs and site recordsخروجیChange raised with its clause referenceEvidence attached to the change
3

Value it by a route the contract names, and say which

سفارش‌های تغییر

Price the change at the contract's own unit rates where the work is measurable, as cost plus the agreed fee off the daywork records where it is not, or as a lump sum with its build-up attached. State in the change which of the three you used and why that route fits this work.

چرا: A number without its method invites the other side to re-price it by a different method, and the method they choose will not be the one that favours you. Naming the route also settles the argument in the right order: first whether the route is right, which is a contract question, and only then whether the number is right, which is an arithmetic one.

ورودیMeasured work or daywork recordsContract unit rates and agreed feeخروجیValuation with its method namedSupporting build-up attached
4

Move the contract price with a reason attached

قراردادها

Approve the change against the contract so the running price shows the original stipulated price, every approved change with its own code and value, and the current price, instead of a total somebody keeps in a spreadsheet cell.

چرا: The contract price is a derived figure, and the only way to defend it at the final account is to walk it backwards to the changes that produced it. A running total nobody can explain is one the payer is entitled to question line by line, at exactly the point in the job where you most need the money.

ورودیApproved change valueOriginal stipulated priceخروجیRunning contract priceEvery movement with a named reason
5

Report the register every month, not at the end

گزارش‌ها

Issue the change register with the monthly report: what has been notified, what is priced and waiting, what is approved, and what the contract price stands at today.

چرا: Changes get sorted out on site and written up later, and later is when the people who agreed them have moved on. A monthly register turns the writing-up into a five-minute review instead of a reconstruction, and it puts the unapproved column in front of the one person who can actually move it.

ورودیNotices, valuations and approvalsخروجیChange register issuedUnapproved changes made visible
ماژول‌ها

ماژول‌های این سناریو

5 / 190 ماژول پلتفرم

The market this case is written for

کانادا

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

بیشتر در بازرگانی و قراردادها

بازرگانی و قراردادها

Turn a change into a paid variation

Capture a scope change while it is fresh, price it as a contract variation on your agreed r…

3 مرحله11 دقیقهباز کردن
بازرگانی و قراردادها

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 مرحله11 دقیقهباز کردن
بازرگانی و قراردادها

Payment application and reconciliation

Value the work put in place this period against the contract, raise the application with th…

3 مرحله12 دقیقهباز کردن