Cases / Commercial & contracts
Commercial & contracts

Record a change under a CCDC-family contract

Give notice of the event inside the period the contract allows, raise the change against the clause it is raised under, value it by one of the routes the contract names and say which, and keep the contract price as a derived figure with a reason for every movement.

5 steps18 minGeneral contractorProject / construction management firmCost consultancy / QS practice

How it works, step by step

5 steps across the platform - what you do at each one, and why it matters.

1

Give the notice before you price anything

Correspondence

Send written notice of the event from the correspondence register on the day it is found, describing what was found and where, and record the date it was given and who received it. Count the period the contract allows in working days against your own site calendar and put that date on the record beside the notice.

Why: The general conditions give a concealed condition, a delay and a claim each their own period counted from the event or from its discovery, and a notice given late can lose an entitlement that would otherwise have been paid in full. Notice first and price second is the order that survives, because the price can be argued and the missed notice cannot.

InThe site event and the day it was foundThe notice period the contract allowsOutNotice given and datedThe day the period runs out
2

Raise it against the clause it is raised under

Variations

Open the change, name the contract and the general condition it is raised under in its reference, and attach the notice, the photographs and the survey that establish the condition you found.

Why: A change carrying its clause reference is a change the consultant can assess without asking what it is for, which is most of the delay in getting one approved. Six months later that reference is also the difference between an approved change and an argument about whether it was ever properly raised.

InThe notice as givenPhotographs and site recordsOutChange raised with its clause referenceEvidence attached to the change
3

Value it by a route the contract names, and say which

Change Orders

Price the change at the contract's own unit rates where the work is measurable, as cost plus the agreed fee off the daywork records where it is not, or as a lump sum with its build-up attached. State in the change which of the three you used and why that route fits this work.

Why: A number without its method invites the other side to re-price it by a different method, and the method they choose will not be the one that favours you. Naming the route also settles the argument in the right order: first whether the route is right, which is a contract question, and only then whether the number is right, which is an arithmetic one.

InMeasured work or daywork recordsContract unit rates and agreed feeOutValuation with its method namedSupporting build-up attached
4

Move the contract price with a reason attached

Contracts

Approve the change against the contract so the running price shows the original stipulated price, every approved change with its own code and value, and the current price, instead of a total somebody keeps in a spreadsheet cell.

Why: The contract price is a derived figure, and the only way to defend it at the final account is to walk it backwards to the changes that produced it. A running total nobody can explain is one the payer is entitled to question line by line, at exactly the point in the job where you most need the money.

InApproved change valueOriginal stipulated priceOutRunning contract priceEvery movement with a named reason
5

Report the register every month, not at the end

Reports

Issue the change register with the monthly report: what has been notified, what is priced and waiting, what is approved, and what the contract price stands at today.

Why: Changes get sorted out on site and written up later, and later is when the people who agreed them have moved on. A monthly register turns the writing-up into a five-minute review instead of a reconstruction, and it puts the unapproved column in front of the one person who can actually move it.

InNotices, valuations and approvalsOutChange register issuedUnapproved changes made visible

More in Commercial & contracts

Commercial & contracts

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 steps11 minOpen