Casos prácticos / Comercial y contratos
Comercial y contratos

Registrar un cambio bajo un contrato de la familia CCDC

Notifica el hecho dentro del plazo que permite el contrato, plantea el cambio contra la cláusula bajo la que se plantea, valóralo por una de las vías que nombra el contrato y di cuál, y lleva el precio del contrato como una cifra derivada con una razón para cada movimiento.

5 pasos18 minContratista generalGestora de proyectos / construcciónConsultoría de costos / QS

Cómo funciona, paso a paso

5 pasos a lo largo de la plataforma - qué haces en cada uno y por qué importa.

1

Give the notice before you price anything

Correspondencia

Send written notice of the event from the correspondence register on the day it is found, describing what was found and where, and record the date it was given and who received it. Count the period the contract allows in working days against your own site calendar and put that date on the record beside the notice.

Por que: The general conditions give a concealed condition, a delay and a claim each their own period counted from the event or from its discovery, and a notice given late can lose an entitlement that would otherwise have been paid in full. Notice first and price second is the order that survives, because the price can be argued and the missed notice cannot.

EntradaThe site event and the day it was foundThe notice period the contract allowsResultadoNotice given and datedThe day the period runs out
2

Raise it against the clause it is raised under

Modificaciones

Open the change, name the contract and the general condition it is raised under in its reference, and attach the notice, the photographs and the survey that establish the condition you found.

Por que: A change carrying its clause reference is a change the consultant can assess without asking what it is for, which is most of the delay in getting one approved. Six months later that reference is also the difference between an approved change and an argument about whether it was ever properly raised.

EntradaThe notice as givenPhotographs and site recordsResultadoChange raised with its clause referenceEvidence attached to the change
3

Value it by a route the contract names, and say which

Órdenes de cambio

Price the change at the contract's own unit rates where the work is measurable, as cost plus the agreed fee off the daywork records where it is not, or as a lump sum with its build-up attached. State in the change which of the three you used and why that route fits this work.

Por que: A number without its method invites the other side to re-price it by a different method, and the method they choose will not be the one that favours you. Naming the route also settles the argument in the right order: first whether the route is right, which is a contract question, and only then whether the number is right, which is an arithmetic one.

EntradaMeasured work or daywork recordsContract unit rates and agreed feeResultadoValuation with its method namedSupporting build-up attached
4

Move the contract price with a reason attached

Contratos

Approve the change against the contract so the running price shows the original stipulated price, every approved change with its own code and value, and the current price, instead of a total somebody keeps in a spreadsheet cell.

Por que: The contract price is a derived figure, and the only way to defend it at the final account is to walk it backwards to the changes that produced it. A running total nobody can explain is one the payer is entitled to question line by line, at exactly the point in the job where you most need the money.

EntradaApproved change valueOriginal stipulated priceResultadoRunning contract priceEvery movement with a named reason
5

Report the register every month, not at the end

Informes

Issue the change register with the monthly report: what has been notified, what is priced and waiting, what is approved, and what the contract price stands at today.

Por que: Changes get sorted out on site and written up later, and later is when the people who agreed them have moved on. A monthly register turns the writing-up into a five-minute review instead of a reconstruction, and it puts the unapproved column in front of the one person who can actually move it.

EntradaNotices, valuations and approvalsResultadoChange register issuedUnapproved changes made visible
Módulos

Módulos de este playbook

5 / 190 módulos de la plataforma

The market this case is written for

Canadá

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Más en Comercial y contratos

Comercial y contratos

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 pasos11 minAbrir