תרחישים / אומדן ותמחור
אומדן ותמחור

מדידת השרטוט לסעיף מקודד בכתב הכמויות

מדדו על השרטוט, הנחיתו את הכמות על סעיף בכתב הכמויות, תנו לסעיף את קוד ה-GB 50500 שלו ואת התיאור של מה שהוא מכסה, ואמתו את הקודים לפני שכתב הכמויות יוצא.

5 שלבים18 דק׳קבלן ראשיייעוץ עלויות / כמויותקבלן משנה מתמחה

איך זה עובד, שלב אחר שלב

5 שלבים לאורך הפלטפורמה - מה עושים בכל שלב ולמה זה חשוב.

1

Measure on the drawing, not off it

מדידות PDF

Open the sheet, set the scale against a dimension printed on the drawing, and measure the areas, lengths and counts you need. The measurements stay on the sheet where they were taken.

למה: A measurement you can point at on the drawing is checkable by somebody else in a minute. The same number in a spreadsheet cell is only as good as the memory of whoever put it there, and on a revision it has to be redone from scratch because nobody can see what it covered.

נכנסDrawing setScale and reference dimensionיוצאMeasurements on the sheetWhat was measured, visible
2

Gather the measurements into quantities

כימות כמויות

Group the measurements into the quantities the bill will actually carry, in the units the measurement rules give for each kind of work, and check the totals against anything you already know about the building.

צילום מסך, שלב 2: Gather the measurements into quantities (כימות כמויות, מדידת השרטוט לסעיף מקודד בכתב הכמויות)
כימות כמויות: Gather the measurements into quantities

למה: The unit is part of the measurement rule, not a formatting choice, and a quantity carried in the wrong one produces a rate that is wrong by a factor rather than by a margin. It is also the last cheap moment to notice that a floor is missing from the take-off.

נכנסMeasurements from the sheetsיוצאQuantities grouped by workUnits the bill will use
3

Land the quantity on a coded bill item

כתב כמויות

Put the quantity on a bill item under the right section and give the item its code. The national schedule gives nine digits; a project bill extends that with a three-digit sequence of its own, so a code of either length is what the bill ends up carrying.

צילום מסך, שלב 3: Land the quantity on a coded bill item (כתב כמויות, מדידת השרטוט לסעיף מקודד בכתב הכמויות)
כתב כמויות: Land the quantity on a coded bill item

למה: The code is the item's identity for the rest of the job. It is what lets a settlement bill be compared against a tender bill after both have been renumbered, and it is what lets two bidders' prices for the same work be set against each other at all.

נכנסThe measured quantityGB 50500 item scheduleיוצאBill item with its code
4

Write the characteristics the rate has to cover

כתב כמויות

Beside the code, write out what the item actually covers: grade, mix, thickness, finish, method, and anything about access or sequence that changes the price. It is free text, so it can say whatever the item needs it to say.

למה: The characteristics are what the code cannot carry, and they differ for every kind of work: what you must state for concrete is nothing like what you must state for windows. An item described in three words gets priced three different ways by three bidders, and the difference becomes yours to absorb at settlement.

נכנסSpecification and drawing notesיוצאItem characteristics written downWhat the rate has to cover
5

Validate the codes, and know what the check does not do

אימות

Run validation on the bill. For a project in China the GB 50500 rules are selected for you: they find items carrying no code at all, and codes that are not a well-formed nine or twelve digits. If your bill form also has a code column of its own, make sure the code being checked is the one on the item rather than a second copy typed elsewhere.

צילום מסך, שלב 5: Validate the codes, and know what the check does not do (אימות, מדידת השרטוט לסעיף מקודד בכתב הכמויות)
אימות: Validate the codes, and know what the check does not do

למה: This checks the shape of the code, not whether that code exists in the national schedule, so a well-formed number nobody ever published passes. Read a clean run as having cleared the typing errors, and read the codes yourself for the ones that matter.

נכנסThe coded billיוצאItems with no codeCodes of the wrong shape
מודולים

המודולים בתרחיש הזה

4 מתוך 190 מודולי הפלטפורמה

The market this case is written for

סין

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

עוד ב-אומדן ותמחור

אומדן ותמחור

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 שלבים8 דק׳פתיחה
אומדן ותמחור

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…