Set up BIM requirements and coordination

Write down what information the employer actually needs from the models, set the federation and coordination rhythm that will deliver it, then check the models that come back carry the properties you asked for.

3 steps10 minBIM / digital consultantDesigner / engineerGeneral contractor

How it works, step by step

3 steps across the platform - what you do at each one, and why it matters.

1

Capture the information requirements

Requirements matrix

Record the employer information requirements as a matrix: which models, at which stages, carrying which properties and to whose standard.

Why: A model handed over without the properties someone needs is a pretty picture, not an asset. Writing the requirement down first is what makes it something you can hold a designer to.

InEmployer briefApplicable standardsOutRequirements matrixProperty schedule
2

Set the coordination cadence

Coordination

Set up the federation and the regular coordination cycle against those requirements: who issues what, when the models come together and how often the team meets to clear conflicts.

Why: Coordination that happens when someone remembers to do it happens too late. A fixed cadence tied to the requirements keeps the disciplines in step instead of colliding on site.

InRequirements matrixDiscipline modelsOutModel federationCoordination schedule
3

Confirm the models comply

BIM viewer

Open the delivered models in the viewer and check the elements actually carry the properties, classifications and level of detail the requirements called for.

Why: The requirement only means something if you check against it. Catching a model short on properties at delivery is a re-issue; catching it at handover is a scramble to rebuild data nobody kept.

InDelivered modelsRequirements matrixOutCompliance checkProperty gaps flagged