نگه‌داشتن برآورد طراحی در چارچوب بودجه مصوب

برآورد سرمایه‌گذاری با نرخی به ازای هر متر مربع پشت آن تعیین کنید، آنچه فرض می‌کند را یادداشت کنید، برآورد طراحی را برای همان محدوده قیمت‌گذاری کنید، و آن را در هر گیت با نسخه مصوب مقایسه کنید.

5 مرحله20 دقیقهسازنده / کارفرمامشاوره هزینه / QSدفتر طراحی / مهندسیدفتر مدیریت پروژه / ساخت

چگونه کار می‌کند، گام به گام

5 گام در سراسر پلتفرم - کاری که در هر گام انجام می‌دهید و چرا اهمیت دارد.

1

Set the investment estimate as a rate, not just a total

برآورد مفهومی

Build the feasibility number from the building type, the gross floor area and the quality level, and read off the rate per square metre it implies as well as the total.

چرا: A total is a fact about a building nobody has designed yet, and a design team cannot work to it. A rate per square metre is a constraint they can test every decision against, which is the whole mechanism of cost-capped design, and it stays comparable when the area moves.

ورودیBuilding type and quality levelGross floor areaخروجیInvestment estimateRate per square metre
2

Write down what the approved number assumes

مبنای برآورد

Record the basis: the scope covered, the standard of finish, the price level and date, what is excluded, and where the rates came from. Keep it with the estimate rather than in the covering email.

چرا: Every argument at the next gate is about whether the design changed or the estimate was wrong, and only the basis can answer it. Without one, a stage that comes in over is always explained as a scope change, and there is nothing on either side that can contradict that.

ورودیThe approved numberWhat it assumedخروجیWritten basis of estimateExclusions on the record
3

Price the design estimate and name the version

صورت مقادیر (BOQ)

Price the design item by item against the same scope the basis describes, and save a named version of the bill at the moment it goes for approval so the approved state can be retrieved exactly.

چرا: The version that was approved is the only meaningful thing to measure later movements against, and it is unrecoverable a month afterwards unless somebody named it at the time. Naming it costs a moment and turns the next comparison from an argument into a report.

ورودیDesign as it standsThe stated basisخروجیDesign estimate priced by itemNamed version at the gate
4

Compare against the approved version at every gate

صورت مقادیر (BOQ)

Set the current bill against the version approved at the previous stage and read the difference by section: which items were added, which quantities grew, which rates moved. Work the rate per square metre out again on the current area and put it beside the one you started with.

چرا: Nothing here declares a limit or returns a verdict, and that is the honest shape of it: the product shows you where the money went and the cap is held by people. What makes that workable is running the comparison at each gate rather than once at the end, because a section that has grown by six percent is a design conversation while a total that has grown by twenty is a re-approval.

ورودیThe bill as it stands nowThe approved versionخروجیWhich sections movedThe rate per square metre now
5

Report the position with the movement explained

گزارش‌ها

Report the stage total, the rate per square metre, the difference against the approved figure and the sections it came from, with a line on each saying whether it was a scope change, a design decision or a price movement.

چرا: An approving body asked to consider a number will ask where it came from, and a report that answers that in advance gets a decision instead of a deferral. Naming the cause per section is also what tells the design team where the savings have to come from, which is the only useful output of the exercise.

ورودیThe gate comparisonخروجیStage report for approvalWhere savings have to come from
ماژول‌ها

ماژول‌های این سناریو

4 / 190 ماژول پلتفرم

The market this case is written for

چین

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

بیشتر در برآورد و هزینه‌یابی

برآورد و هزینه‌یابی

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 مرحله8 دقیقهباز کردن
برآورد و هزینه‌یابی

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 مرحله12 دقیقهباز کردن
برآورد و هزینه‌یابی

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 مرحله11 دقیقهباز کردن