Mga Kaso / Pag-estimate at pagpepresyo
Pag-estimate at pagpepresyo

Bumuo ng all-in labour rate gamit ang Canadian burden

Hatiin ang oras-oras na rate na ginagamit mo sa loob ng maraming taon sa base wage at mga pinangalanang kontribusyon sa ibabaw nito, magpanatili ng isang template kada probinsya dahil probinsyal ang burden, at itala kung saan nanggaling ang bawat rate at ang petsa na naging epektibo ito.

5 hakbang20 minGeneral ContractorEspesyalistang SubcontractorCost Consultancy / QS Practice

Paano ito gumagana, hakbang-hakbang

5 hakbang sa buong platform - ano ang gagawin mo sa bawat isa at bakit mahalaga ito.

1

Start from the base wage, one province at a time

Rate ng Labor

Create a rate template for the trade, enter the base hourly wage, and name the template for the province it belongs to, because the same trade carries a different burden in every province it works in.

Bakit: One template covering two provinces has to average something, and an averaged burden is precisely the thing you cannot explain when a bid gets queried. A template per province costs a few minutes to set up and is the only version that survives being asked where the number came from.

PapasokTrade and provinceBase hourly wageLumalabasOne rate template per provinceBase wage on record
2

Add each contribution as its own named line

Rate ng Labor

Build the stack on the wage as separate lines: pension contribution, employment insurance at the employer multiple, vacation pay, statutory holiday pay, workers compensation at the classification unit rate for this trade, and the benefit contributions that apply. Keep percentages as percentages and fixed amounts as amounts rather than blending them into one uplift.

Bakit: A single burden percentage hides the fact that its parts move independently and on different dates. Workers compensation in particular is rated by classification unit, so it changes when the work the crew does changes, not when the calendar turns, and that is the movement a blended uplift will never show you.

PapasokContribution rates for the provinceClassification unit for the tradeLumalabasNamed burden stackAll-in rate derived from its parts
3

Write down where each rate came from and when it applied

Batayan ng Estimate

Record in the basis of estimate the source of every contribution in the stack, the body that administers it, and the date that rate took effect, so the whole stack can be re-checked against its authorities in an afternoon.

Bakit: When the rate moves you will be asked which line moved, and the answer has to be a citation rather than a memory. It is also what turns a rate into something a colleague can maintain after you, which is the whole difference between a company rate and a personal one.

PapasokThe burden stack as builtSource and effective date per lineLumalabasSourced and dated rate basisA rate somebody else can maintain
4

Point the assemblies at the rate, not at a typed number

Mga Assembly

Build the crew compositions and assemblies against the rate template rather than against a figure typed into each one, so that a change to any contribution reprices everything that depends on it.

Bakit: A rate typed into forty assemblies is forty rates, and they will not all be updated on the day a premium changes. Pointing at the template is what makes the next update a single edit instead of a search that finds most of them.

PapasokThe rate templateCrew compositions and assembliesLumalabasAssemblies priced off one rateUpdates that propagate
5

Test the built rate against what the job actually cost

Mga Ulat

Report the built rate against recorded hours and paid cost on a job that has finished, component by component, and correct the line that is wrong rather than adjusting the total until it matches.

Bakit: A stack is only worth building if it gets corrected, and correcting a total teaches nobody anything. Fifteen years of experience tells you what the number should be; the stack tells you which part of it drifted, and only one of those two can be handed to the next estimator.

PapasokThe built all-in rateRecorded hours and paid costLumalabasVariance by componentA corrected line, not a corrected total
Mga Module

Mga Module sa Playbook na Ito

4 / 190 na module ng platform

The market this case is written for

Canada

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Higit pa sa Pag-estimate at pagpepresyo

Pag-estimate at pagpepresyo

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 hakbang12 minBukas
Pag-estimate at pagpepresyo

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 hakbang11 minBukas