Assess an extension of time with programme impact

Log the delay event with its evidence, insert it into the programme to measure the real impact on completion, set out the entitlement and submit the extension of time notice under the contract.

4 koraka12 minGlavni izvođačSpecijalizirani podizvođačKonzultant za troškove / QS

Kako funkcionira, korak po korak

4 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Log the delay event

Dokazi zahtjeva

Log the delay event with its cause and gather the contemporaneous records that prove it: the diary entries, the late instruction, the photos, the correspondence around the date it hit.

Zašto: An extension of time claim lives or dies on contemporaneous evidence. Assembling it while the event is fresh is what turns a plausible story into a claim that gets awarded.

UlazDelay eventContemporaneous recordsRezultatEvidence pack
2

Measure the programme impact

Napredni raspored

Insert the delay into the programme and compare the impacted completion against the baseline, so the days claimed come from a network analysis rather than an assertion.

Zašto: Only a delay on the critical path moves the completion date. Showing the impact through the programme is what separates a genuine extension from a claim for a delay that had float to absorb it.

UlazBaseline programmeDelay eventRezultatImpacted programmeDays of delay
3

Set out the entitlement

Izmjene ugovora

Test the delay against the contract: which cause is a relevant, excusable event, how the clauses treat it, and how many days you are entitled to claim.

Zašto: Impact is not the same as entitlement. Tying the days to the specific clause is what makes the claim contractual instead of a grievance, and what an assessor can actually award against.

UlazDays of delayContract clausesRezultatAssessed entitlement
4

Submit the notice

Ugovori

Submit the extension of time notice and its particulars within the contractual time limit, with the impacted programme and the evidence attached.

Zašto: Many good claims are lost simply by being late. Submitting inside the notice period, complete and evidenced, is what keeps the entitlement alive and the completion date defensible.

UlazAssessed entitlementRezultatExtension of time notice