Assess an extension of time with programme impact

Log the delay event with its evidence, insert it into the programme to measure the real impact on completion, set out the entitlement and submit the extension of time notice under the contract.

4 bước12 phútNhà thầu chínhNhà thầu phụ chuyên ngànhTư vấn chi phí / QS

Cách hoạt động, từng bước một

4 bước xuyên suốt nền tảng - bạn làm gì ở mỗi bước và vì sao điều đó quan trọng.

1

Log the delay event

Bằng chứng khiếu nại

Log the delay event with its cause and gather the contemporaneous records that prove it: the diary entries, the late instruction, the photos, the correspondence around the date it hit.

Tại sao: An extension of time claim lives or dies on contemporaneous evidence. Assembling it while the event is fresh is what turns a plausible story into a claim that gets awarded.

Đầu vàoDelay eventContemporaneous recordsĐầu raEvidence pack
2

Measure the programme impact

Lịch trình nâng cao

Insert the delay into the programme and compare the impacted completion against the baseline, so the days claimed come from a network analysis rather than an assertion.

Tại sao: Only a delay on the critical path moves the completion date. Showing the impact through the programme is what separates a genuine extension from a claim for a delay that had float to absorb it.

Đầu vàoBaseline programmeDelay eventĐầu raImpacted programmeDays of delay
3

Set out the entitlement

Lệnh thay đổi

Test the delay against the contract: which cause is a relevant, excusable event, how the clauses treat it, and how many days you are entitled to claim.

Tại sao: Impact is not the same as entitlement. Tying the days to the specific clause is what makes the claim contractual instead of a grievance, and what an assessor can actually award against.

Đầu vàoDays of delayContract clausesĐầu raAssessed entitlement
4

Submit the notice

Hợp đồng

Submit the extension of time notice and its particulars within the contractual time limit, with the impacted programme and the evidence attached.

Tại sao: Many good claims are lost simply by being late. Submitting inside the notice period, complete and evidenced, is what keeps the entitlement alive and the completion date defensible.

Đầu vàoAssessed entitlementĐầu raExtension of time notice