Assess an extension of time with programme impact

Log the delay event with its evidence, insert it into the programme to measure the real impact on completion, set out the entitlement and submit the extension of time notice under the contract.

4단계12 분종합건설사전문건설사원가 컨설턴트 / 적산사

작동 방식, 단계별로

플랫폼 전반에 걸친 4단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Log the delay event

클레임 증거

Log the delay event with its cause and gather the contemporaneous records that prove it: the diary entries, the late instruction, the photos, the correspondence around the date it hit.

이유: An extension of time claim lives or dies on contemporaneous evidence. Assembling it while the event is fresh is what turns a plausible story into a claim that gets awarded.

입력Delay eventContemporaneous records결과Evidence pack
2

Measure the programme impact

고급 일정

Insert the delay into the programme and compare the impacted completion against the baseline, so the days claimed come from a network analysis rather than an assertion.

이유: Only a delay on the critical path moves the completion date. Showing the impact through the programme is what separates a genuine extension from a claim for a delay that had float to absorb it.

입력Baseline programmeDelay event결과Impacted programmeDays of delay
3

Set out the entitlement

변경 지시

Test the delay against the contract: which cause is a relevant, excusable event, how the clauses treat it, and how many days you are entitled to claim.

이유: Impact is not the same as entitlement. Tying the days to the specific clause is what makes the claim contractual instead of a grievance, and what an assessor can actually award against.

입력Days of delayContract clauses결과Assessed entitlement
4

Submit the notice

계약

Submit the extension of time notice and its particulars within the contractual time limit, with the impacted programme and the evidence attached.

이유: Many good claims are lost simply by being late. Submitting inside the notice period, complete and evidenced, is what keeps the entitlement alive and the completion date defensible.

입력Assessed entitlement결과Extension of time notice