تخمینہ سازی اور لاگت

Calculate with your own rates for the EFB price sheets

Build the Mittellohn, keep your own material and plant rates, compose the recipes that carry them and calculate every position from resources, so each unit price opens down to the hours and quantities behind it.

6 مراحل12 منٹجنرل کنٹریکٹرخصوصی سب کنٹریکٹرکاسٹ کنسلٹنسی / QS فرم

یہ کیسے کام کرتا ہے، قدم بہ قدم

6 قدم پوری پلیٹ فارم میں - ہر قدم پر کیا کرنا ہے اور یہ کیوں اہم ہے۔

1

Load the wage with its social costs

لیبر ریٹس

Enter the agreed base hourly wage for a grade, then add what the employer carries on top of it: social insurance, holiday and public holiday pay, continued pay when someone is sick, pension, the training levy, and the site allowances and travel money this job pays.

کیوں: The bare wage is not what an hour costs you, and the gap is regularly a third or more. Every labour line in the tender is understated by whatever you leave out here, and the error only shows up once the job is running.

اندر جاتا ہےWage agreementBase wage per gradeباہر آتا ہےLoaded hourly costLabour burden in percent
2

Blend the crew into one Mittellohn

لیبر ریٹس

List the crew that actually does the work, the foreman, the skilled workers and the labourers, each with a head count and its loaded rate, and let the page blend them into the single average hourly rate the calculation runs on. Save it as a template so the next tender starts from it.

کیوں: Work is priced in crew hours, not in one person's wage. One Mittellohn behind every position keeps the labour figure consistent across the whole bill, and it is the first line a Vergabestelle looks for when it asks for the EFB price sheets.

اندر جاتا ہےLoaded rate per gradeCrew compositionباہر آتا ہےMittellohn per hourSaved rate template
3

Keep material and plant rates as your own master data

ریسورس کیٹلاگ

Put your own resources into the catalog next to the imported reference ones: material prices from the quotes your suppliers actually gave you, and an hourly cost for each machine you own or hire, each with its unit and its price.

کیوں: Your own prices are what separates a calculation from a guess, because they are the prices you will really pay. When steel or diesel moves you correct one rate, and every recipe and position standing on it moves with it instead of being retyped line by line.

اندر جاتا ہےSupplier quotesOwned and hired plant costsباہر آتا ہےPriced material resourcesPriced equipment resources
4

Compose the recipe for one unit of work

اسمبلیز

Build an assembly for one unit of finished work, say a square metre of wall formwork: the crew hours per unit at the Mittellohn, the material with its waste allowance, and the machine hours the work needs. The component lines add up to the rate.

کیوں: The recipe is where your own output figures meet your own prices. Written down once it prices the same work the same way on every tender, and it is what lets you explain a rate a year later instead of defending a number nobody can reconstruct.

اندر جاتا ہےMittellohn per hourMaterial and equipment ratesHours per unitباہر آتا ہےAssembly with component linesComposite unit rate
5

Calculate the positions from the recipes

مقدار کا بل (BOQ)

Open the bill for this project and price its positions from the assemblies rather than typing a rate into the cell. Each position then carries its own labour, material and plant lines, and the grid can show that split beside the unit price.

کیوں: A unit price assembled from resources survives a question. When the client asks how you got to the figure you open the position and show the hours and the quantities, instead of promising to look into it and hoping the answer is close.

اندر جاتا ہےBill positions and quantitiesAssembliesباہر آتا ہےPriced positionsResource lines per position
6

Open the price down to its resources

ریسورس خلاصہ

Read the resource statement for the whole estimate: the total labour hours and their cost, and the quantity and cost of every material, machine and subcontract line behind the offer. Export it when you need the figures outside the platform.

کیوں: This is the breakdown the EFB price sheets 221 and 223 expect a bidder to file with a public tender. Because it is read straight off the priced positions, producing it is a look and an export rather than a weekend spent rebuilding the calculation in a spreadsheet.

اندر جاتا ہےPriced positionsResource linesباہر آتا ہےLabour, material and plant statementFigures for the EFB price sheets
ماڈیولز

اس سیناریو کے ماڈیولز

5 / 184 پلیٹ فارم ماڈیولز

تخمینہ سازی اور لاگت میں مزید

تخمینہ سازی اور لاگت

بھیجنے سے پہلے اسٹیمیٹ چیک کریں

پرائسڈ بل کو ویلیڈیشن رولز سے گزاریں، ہر انتباہ اور خرابی صاف کریں، پھر صاف رپورٹ ایکسپورٹ ک…

3 مراحل8 منٹکھولیں
تخمینہ سازی اور لاگت

لاگت ڈیٹا بیس سے تخمینہ لگائیں

حقیقی لاگت ڈیٹا بیس سے قیمت شدہ آئٹمز نکالیں، ان سے بل بنائیں، بار بار آنے والے بلڈ اپس کو ا…

4 مراحل12 منٹکھولیں
تخمینہ سازی اور لاگت

لاگت کے رسک سے کنٹنجنسی مقرر کریں

ایک نکاتی تخمینے کو ایک دائرے میں بدلیں، حقیقی طور پر غیر یقینی لائنوں پر مونٹے کارلو چلائیں…

3 مراحل11 منٹکھولیں