Fall / Kalkylering och kostnader
Kalkylering och kostnader

Kalkylera med dina egna priser för EFB-prisbladen

Bygg Mittellohn, håll dina egna material- och maskintaxor, sätt samman recepten som bär dem och kalkylera varje post från resurser, så att varje á-pris öppnas ner till timmarna och mängderna bakom det.

6 steg12 minGeneralentreprenörSpecialunderentreprenörKostnadsrådgivning / QS

Så fungerar det, steg för steg

6 steg genom plattformen - vad du gör i varje och varför det spelar roll.

1

Load the wage with its social costs

Arbetspriser

Enter the agreed base hourly wage for a grade, then add what the employer carries on top of it: social insurance, holiday and public holiday pay, continued pay when someone is sick, pension, the training levy, and the site allowances and travel money this job pays.

Skärmbild, steg 1: Load the wage with its social costs (Arbetspriser, Kalkylera med dina egna priser för EFB-prisbladen)
Arbetspriser: Load the wage with its social costs

Varför: The bare wage is not what an hour costs you, and the gap is regularly a third or more. Every labour line in the tender is understated by whatever you leave out here, and the error only shows up once the job is running.

IndataWage agreementBase wage per gradeResultatLoaded hourly costLabour burden in percent
2

Blend the crew into one Mittellohn

Arbetspriser

List the crew that actually does the work, the foreman, the skilled workers and the labourers, each with a head count and its loaded rate, and let the page blend them into the single average hourly rate the calculation runs on. Save it as a template so the next tender starts from it.

Skärmbild, steg 2: Blend the crew into one Mittellohn (Arbetspriser, Kalkylera med dina egna priser för EFB-prisbladen)
Arbetspriser: Blend the crew into one Mittellohn

Varför: Work is priced in crew hours, not in one person's wage. One Mittellohn behind every position keeps the labour figure consistent across the whole bill, and it is the first line a Vergabestelle looks for when it asks for the EFB price sheets.

IndataLoaded rate per gradeCrew compositionResultatMittellohn per hourSaved rate template
3

Keep material and plant rates as your own master data

Resurskatalog

Put your own resources into the catalog next to the imported reference ones: material prices from the quotes your suppliers actually gave you, and an hourly cost for each machine you own or hire, each with its unit and its price.

Skärmbild, steg 3: Keep material and plant rates as your own master data (Resurskatalog, Kalkylera med dina egna priser för EFB-prisbladen)
Resurskatalog: Keep material and plant rates as your own master data

Varför: Your own prices are what separates a calculation from a guess, because they are the prices you will really pay. When steel or diesel moves you correct one rate, and every recipe and position standing on it moves with it instead of being retyped line by line.

IndataSupplier quotesOwned and hired plant costsResultatPriced material resourcesPriced equipment resources
4

Compose the recipe for one unit of work

Sammansatta kalkylrader

Build an assembly for one unit of finished work, say a square metre of wall formwork: the crew hours per unit at the Mittellohn, the material with its waste allowance, and the machine hours the work needs. The component lines add up to the rate.

Skärmbild, steg 4: Compose the recipe for one unit of work (Sammansatta kalkylrader, Kalkylera med dina egna priser för EFB-prisbladen)
Sammansatta kalkylrader: Compose the recipe for one unit of work

Varför: The recipe is where your own output figures meet your own prices. Written down once it prices the same work the same way on every tender, and it is what lets you explain a rate a year later instead of defending a number nobody can reconstruct.

IndataMittellohn per hourMaterial and equipment ratesHours per unitResultatAssembly with component linesComposite unit rate
5

Calculate the positions from the recipes

Mängdförteckning

Open the bill for this project and price its positions from the assemblies rather than typing a rate into the cell. Each position then carries its own labour, material and plant lines, and the grid can show that split beside the unit price.

Varför: A unit price assembled from resources survives a question. When the client asks how you got to the figure you open the position and show the hours and the quantities, instead of promising to look into it and hoping the answer is close.

IndataBill positions and quantitiesAssembliesResultatPriced positionsResource lines per position
6

Open the price down to its resources

Resurssammanställning

Read the resource statement for the whole estimate: the total labour hours and their cost, and the quantity and cost of every material, machine and subcontract line behind the offer. Export it when you need the figures outside the platform.

Skärmbild, steg 6: Open the price down to its resources (Resurssammanställning, Kalkylera med dina egna priser för EFB-prisbladen)
Resurssammanställning: Open the price down to its resources

Varför: This is the breakdown the EFB price sheets 221 and 223 expect a bidder to file with a public tender. Because it is read straight off the priced positions, producing it is a look and an export rather than a weekend spent rebuilding the calculation in a spreadsheet.

IndataPriced positionsResource linesResultatLabour, material and plant statementFigures for the EFB price sheets
Moduler

Moduler i denna playbook

5 / 190 plattformsmoduler

The market this case is written for

Tyskland

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • DIN 276
  • GAEB XML
  • VOB/B

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Mer inom Kalkylering och kostnader

Kalkylering och kostnader

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 steg12 minÖppna
Kalkylering och kostnader

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 steg11 minÖppna