Calculate with your own rates for the EFB price sheets

Build the Mittellohn, keep your own material and plant rates, compose the recipes that carry them and calculate every position from resources, so each unit price opens down to the hours and quantities behind it.

6단계12 분종합건설사전문건설사원가 컨설팅 / 적산 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 6단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Load the wage with its social costs

노무 단가

Enter the agreed base hourly wage for a grade, then add what the employer carries on top of it: social insurance, holiday and public holiday pay, continued pay when someone is sick, pension, the training levy, and the site allowances and travel money this job pays.

이유: The bare wage is not what an hour costs you, and the gap is regularly a third or more. Every labour line in the tender is understated by whatever you leave out here, and the error only shows up once the job is running.

입력Wage agreementBase wage per grade결과Loaded hourly costLabour burden in percent
2

Blend the crew into one Mittellohn

노무 단가

List the crew that actually does the work, the foreman, the skilled workers and the labourers, each with a head count and its loaded rate, and let the page blend them into the single average hourly rate the calculation runs on. Save it as a template so the next tender starts from it.

이유: Work is priced in crew hours, not in one person's wage. One Mittellohn behind every position keeps the labour figure consistent across the whole bill, and it is the first line a Vergabestelle looks for when it asks for the EFB price sheets.

입력Loaded rate per gradeCrew composition결과Mittellohn per hourSaved rate template
3

Keep material and plant rates as your own master data

자원 카탈로그

Put your own resources into the catalog next to the imported reference ones: material prices from the quotes your suppliers actually gave you, and an hourly cost for each machine you own or hire, each with its unit and its price.

이유: Your own prices are what separates a calculation from a guess, because they are the prices you will really pay. When steel or diesel moves you correct one rate, and every recipe and position standing on it moves with it instead of being retyped line by line.

입력Supplier quotesOwned and hired plant costs결과Priced material resourcesPriced equipment resources
4

Compose the recipe for one unit of work

일위대가

Build an assembly for one unit of finished work, say a square metre of wall formwork: the crew hours per unit at the Mittellohn, the material with its waste allowance, and the machine hours the work needs. The component lines add up to the rate.

이유: The recipe is where your own output figures meet your own prices. Written down once it prices the same work the same way on every tender, and it is what lets you explain a rate a year later instead of defending a number nobody can reconstruct.

입력Mittellohn per hourMaterial and equipment ratesHours per unit결과Assembly with component linesComposite unit rate
5

Calculate the positions from the recipes

내역서

Open the bill for this project and price its positions from the assemblies rather than typing a rate into the cell. Each position then carries its own labour, material and plant lines, and the grid can show that split beside the unit price.

이유: A unit price assembled from resources survives a question. When the client asks how you got to the figure you open the position and show the hours and the quantities, instead of promising to look into it and hoping the answer is close.

입력Bill positions and quantitiesAssemblies결과Priced positionsResource lines per position
6

Open the price down to its resources

자원 요약

Read the resource statement for the whole estimate: the total labour hours and their cost, and the quantity and cost of every material, machine and subcontract line behind the offer. Export it when you need the figures outside the platform.

이유: This is the breakdown the EFB price sheets 221 and 223 expect a bidder to file with a public tender. Because it is read straight off the priced positions, producing it is a look and an export rather than a weekend spent rebuilding the calculation in a spreadsheet.

입력Priced positionsResource lines결과Labour, material and plant statementFigures for the EFB price sheets
모듈

이 플레이북의 모듈

플랫폼 184개 모듈 중 5

적산 및 원가 카테고리의 더 보기

적산 및 원가

발송 전 견적 점검

산출된 내역서를 검증 규칙에 통과시켜 모든 경고와 오류를 해결한 뒤, 발주자에게 바로 전달할 수 있는 깨끗한 보고서를 내보냅니다.

3단계8 분열기
적산 및 원가

원가 데이터베이스로 견적 산정하기

실제 원가 데이터베이스에서 가격 항목을 가져와 내역서를 작성하고, 반복되는 조합을 어셈블리로 묶은 뒤, 입찰 금액을 확정하기 전에 검토를 실행합니다.

4단계12 분열기
적산 및 원가

비용 리스크로 예비비 산정하기

단일 값 견적을 범위로 바꾸고, 실제로 불확실한 항목에 대해 몬테카를로 시뮬레이션을 실행하여 P50~P90 분포를 읽고, 항목별로 근거를 설명할 수 있는 예비비를 설…

3단계11 분열기