Answer a GAEB inquiry as a subcontractor

Take the contractor's GAEB inquiry into your own LV, price your trade with your own rates, decide between Hauptangebot and Nebenangebot, and send the X84 back before the deadline.

7 خطوة11 دقيقةمقاول باطن متخصص

كيف يعمل، خطوة بخطوة

7 خطوات عبر المنصة - ما تفعله في كل منها ولماذا يهم.

1

Log the inquiry and its deadline

إدارة العطاءات

Log the inquiry the general contractor sent you: which trade package it covers, the Abgabefrist and the Bindefrist you are held to, and whether the letter admits Nebenangebote at all.

لماذا: Whether an alternate is allowed is decided by the inquiry, not by you. Reading that together with the deadline on day one is what stops a good idea being set aside on a formality, or a finished price arriving an hour late.

المدخلاتInquiry from the contractorGAEB X83 fileالمخرجاتLogged inquiryAbgabefrist on recordNebenangebot rule
2

Import the X83 into your own LV

تبادل GAEB

Drop the X83 on the import tab, check the parsed positions in the preview and take them into a fresh LV in your own project. Ordinal numbers, quantities, units and Langtext arrive exactly as the contractor issued them.

لماذا: Retyping the contractor's LV is where a transposed quantity or a dropped position becomes a loss you carry to site. Importing keeps your price tied to their numbering, so every line answers the line they asked about.

المدخلاتGAEB X83 fileYour projectالمخرجاتLV with positionsOriginal OZ numbering
3

Cut the bill down to your trade

جدول الكميات

Work through the imported LV and keep the titles and positions that belong to your trade, whether that is Trockenbau or TGA, and mark what is outside your scope. Check the quantities against your own take before you price a line.

لماذا: A Nachunternehmer prices one trade out of a bill written for the whole building. Drawing that boundary first keeps your offer comparable, and checking the quantity is what stops you carrying the planner's undermeasure at your own risk.

المدخلاتImported LVYour trade scopeالمخرجاتYour trade packageExclusions noted
4

Price it with your own rates

كتالوج الموارد

Price every position from your own rates and assemblies instead of somebody else's guide price: labour, material, plant and the surcharge you actually carry, each line read against its Langtext as you go.

لماذا: Your own rate is the only number you can defend when the contractor asks how you got there. Reading the Langtext while you price is where you find the scaffold, the working hours or the tolerance that would otherwise be free work.

المدخلاتUnpriced positionsYour own ratesالمخرجاتPriced HauptangebotQualifications noted
5

Separate Hauptangebot from Nebenangebot

جدول الكميات

Keep the priced LV as your Hauptangebot, line for line as asked. Where your method really is better, copy the bill into a second LV, change only the positions your solution touches and write the reason next to each one.

لماذا: A Nebenangebot wins work when it is a clean second offer the contractor can compare position by position. Mixing the better idea into the main bill instead risks the whole offer being set aside as not answering the tender.

المدخلاتPriced HauptangebotYour better methodالمخرجاتHauptangebot LVNebenangebot LVReason per changed position
6

Validate both bills before they go out

التحقق

Run both LVs through validation: no position left at zero, no quantity that no longer ties back to the X83, and the structure the return file has to honour still intact.

لماذا: A single unpriced position can void the whole submission, and nobody reads several hundred lines twice at four in the afternoon on the deadline day. Validation is the second pair of eyes that takes a minute.

المدخلاتHauptangebot LVNebenangebot LVالمخرجاتValidation reportGaps closed
7

Export the X84 and submit on time

تبادل GAEB

Export each priced LV on the export tab as its own X84, name the files so the contractor sees at a glance which one is the Hauptangebot and which the Nebenangebot, and send them with your covering letter before the Abgabefrist.

لماذا: An X84 reads straight into the contractor's bid comparison, so your prices land in the evaluation without anybody rekeying them. Two clearly named files are what let your alternate be judged rather than put aside.

المدخلاتValidated billsAbgabefristالمخرجاتX84 HauptangebotX84 NebenangebotSubmission on record
الوحدات

وحدات هذا الدليل

5 / 184 من وحدات المنصة

المزيد في المناقصات والمشتريات

المناقصات والمشتريات

إجراء مناقصة من BOQ

اطرح جدول كميات مسعّراً في السوق: حزّمه، وادعُ مقاولي الباطن، وسوِّ عروضهم، وأرسِ على الفائز…

5 خطوة12 دقيقةفتح
المناقصات والمشتريات

توريد المواد من BOQ

اشترِ الكميات التي سعّرتها بالفعل: أنشئ طلب شراء من الجدول، وضع الأمر لدى مورّد، وسجّل استلا…

4 خطوة10 دقيقةفتح
المناقصات والمشتريات

مقارنة العطاءات والترسية

خذ مجلد عطاءات مُعادة لا تتطابق تماماً، وأرجعها إلى النطاق نفسه، وسلّم العميل قرار ترسية يصم…

3 خطوة12 دقيقةفتح