Answer a GAEB inquiry as a subcontractor

Take the contractor's GAEB inquiry into your own LV, price your trade with your own rates, decide between Hauptangebot and Nebenangebot, and send the X84 back before the deadline.

7 алхам11 минМэргэшсэн дэд гүйцэтгэгч

Хэрхэн ажилладаг, алхам алхмаар

Платформ даяар 7 алхам - алхам бүрт юу хийх, яагаад чухал болохыг.

1

Log the inquiry and its deadline

Тендерийн удирдлага

Log the inquiry the general contractor sent you: which trade package it covers, the Abgabefrist and the Bindefrist you are held to, and whether the letter admits Nebenangebote at all.

Яагаад: Whether an alternate is allowed is decided by the inquiry, not by you. Reading that together with the deadline on day one is what stops a good idea being set aside on a formality, or a finished price arriving an hour late.

ОролтInquiry from the contractorGAEB X83 fileҮр дүнLogged inquiryAbgabefrist on recordNebenangebot rule
2

Import the X83 into your own LV

GAEB солилцоо

Drop the X83 on the import tab, check the parsed positions in the preview and take them into a fresh LV in your own project. Ordinal numbers, quantities, units and Langtext arrive exactly as the contractor issued them.

Яагаад: Retyping the contractor's LV is where a transposed quantity or a dropped position becomes a loss you carry to site. Importing keeps your price tied to their numbering, so every line answers the line they asked about.

ОролтGAEB X83 fileYour projectҮр дүнLV with positionsOriginal OZ numbering
3

Cut the bill down to your trade

Ажил материалын жагсаалт

Work through the imported LV and keep the titles and positions that belong to your trade, whether that is Trockenbau or TGA, and mark what is outside your scope. Check the quantities against your own take before you price a line.

Яагаад: A Nachunternehmer prices one trade out of a bill written for the whole building. Drawing that boundary first keeps your offer comparable, and checking the quantity is what stops you carrying the planner's undermeasure at your own risk.

ОролтImported LVYour trade scopeҮр дүнYour trade packageExclusions noted
4

Price it with your own rates

Нөөцийн Каталог

Price every position from your own rates and assemblies instead of somebody else's guide price: labour, material, plant and the surcharge you actually carry, each line read against its Langtext as you go.

Яагаад: Your own rate is the only number you can defend when the contractor asks how you got there. Reading the Langtext while you price is where you find the scaffold, the working hours or the tolerance that would otherwise be free work.

ОролтUnpriced positionsYour own ratesҮр дүнPriced HauptangebotQualifications noted
5

Separate Hauptangebot from Nebenangebot

Ажил материалын жагсаалт

Keep the priced LV as your Hauptangebot, line for line as asked. Where your method really is better, copy the bill into a second LV, change only the positions your solution touches and write the reason next to each one.

Яагаад: A Nebenangebot wins work when it is a clean second offer the contractor can compare position by position. Mixing the better idea into the main bill instead risks the whole offer being set aside as not answering the tender.

ОролтPriced HauptangebotYour better methodҮр дүнHauptangebot LVNebenangebot LVReason per changed position
6

Validate both bills before they go out

Шалгалт

Run both LVs through validation: no position left at zero, no quantity that no longer ties back to the X83, and the structure the return file has to honour still intact.

Яагаад: A single unpriced position can void the whole submission, and nobody reads several hundred lines twice at four in the afternoon on the deadline day. Validation is the second pair of eyes that takes a minute.

ОролтHauptangebot LVNebenangebot LVҮр дүнValidation reportGaps closed
7

Export the X84 and submit on time

GAEB солилцоо

Export each priced LV on the export tab as its own X84, name the files so the contractor sees at a glance which one is the Hauptangebot and which the Nebenangebot, and send them with your covering letter before the Abgabefrist.

Яагаад: An X84 reads straight into the contractor's bid comparison, so your prices land in the evaluation without anybody rekeying them. Two clearly named files are what let your alternate be judged rather than put aside.

ОролтValidated billsAbgabefristҮр дүнX84 HauptangebotX84 NebenangebotSubmission on record
Модулиуд

Энэ тоглолтын модулиуд

Платформын 184 модулиас 5

Тендер ба худалдан авалт дахь бусад

Тендер ба худалдан авалт

BOQ-оос материал худалдан авах

Аль хэдийн үнэлсэн тоо хэмжээгээ худалдаж ав: данснаас хэрэгцээний хүсэлт гарга, ханган нийл…

4 алхам10 минНээх