Turn a change into a paid variation
Capture a scope change while it is fresh, price it as a contract variation on your agreed r…
Oznamte změnu, dokud je ještě faktem, naceňte ji způsobem, který smlouva předepisuje, prokažte zpoždění ze záznamů pořízených v té době, ukažte ho vůči harmonogramu, a uzavřete ho jako pokyn a dohodnuté datum místo jako nárok na konci.
6 kroků napříč platformou - co na každém uděláte a proč na tom záleží.
Raise the notice as soon as the change appears, addressed to the party the contract names, carrying the date it was raised and the date a response is due. Under NEC4 this is the compensation event notification; under JCT it is the notice that starts the extension of time running.

Proč: Both forms make the notice the thing that preserves the entitlement, and NEC4 says so out loud: a compensation event not notified within eight weeks of the contractor becoming aware of it is generally not assessed at all. A notice raised on the day costs a minute; the same notice raised in the final account costs the entitlement.
Turn the notice into a variation request and price it: measured work at bill rates where the rates apply, pro rata where the character of the work is similar, and dayworks where neither fits. Record the effect on time alongside the effect on cost, because under NEC4 the two are assessed together.

Proč: The valuation rules exist so that a change is priced the same way whoever prices it, and the disputes happen exactly where somebody skipped them. Dayworks in particular are worth what the signed sheets say and nothing more, so a daywork record agreed on the day beats a well argued rate three months later.
Build the evidence pack out of what was already recorded: the diary entries for the days in question, the correspondence, the RFIs, the approvals and the earlier notices. The pack is ordered deterministically and carries a digest, so both sides can reproduce the same bundle.

Proč: An entitlement is decided on contemporaneous records, and contemporaneous means written while it was happening by somebody who did not yet know it would matter. A pack drawn from the diary and the correspondence is that. A narrative written afterwards from memory reads as advocacy even when every word of it is true.
Take the accepted programme and show what the event did to it: which activities moved, how much float was available to absorb it, and whether the completion date actually moved. That is the extension of time argument under JCT and the assessment of the compensation event under NEC4.
Proč: Delay is a property of the critical path, and a job can lose three weeks on an activity that was never critical and still finish on time. Showing the effect on the programme separates an extension of time you are given from one you argue about, and it also tells you honestly when there is nothing here worth chasing.
Convert the agreed request into a variation order carrying the final cost effect and the final effect on time, and record the extension of time decision with its cause: employer caused, neutral, contractor caused or concurrent.

Proč: An open variation is a number two parties each remember differently. Closing it fixes both halves at once, and recording the cause of the delay is what stops the same fact being re-argued at the final account under a different name and a fresh set of adjectives.
Post the variation order against the contract so the adjusted contract sum moves with it, and let the next interim valuation pick it up. The final account is then the running total rather than an exercise in reconciliation.

Proč: A variation agreed but never posted is the commonest reason a final account comes as a surprise. Carrying each one into the contract sum as it is agreed keeps both parties working to the same number the whole way through, and turns the final account into a signature rather than a negotiation.
4 / 190 modulů platformy
Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.
Standards it follows
You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.
The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.
Capture a scope change while it is fresh, price it as a contract variation on your agreed r…
Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…
Value the work put in place this period against the contract, raise the application with th…