Případy / Rozpočtování a náklady
Rozpočtování a náklady

Provést odhad od třídy D po třídu A

Uveďte, z čeho byl každý odhad sestaven a do jaké třídy žebříčku ho to řadí, veďte návrhovou rezervu, kterou třída očekává, odděleně od rizika, sečtěte náklad jak podle prvku, tak podle oboru, a valorizujte k polovině doby výstavby, ne ke dni, kdy zakázka skončí.

5 kroků20 minNákladové poradenství / rozpočtářstvíDeveloper / klientProjektová / stavební manažerská firmaGenerální dodavatel

Jak to funguje, krok za krokem

5 kroků napříč platformou - co na každém uděláte a proč na tom záleží.

1

Say what this estimate was prepared from

Východiska rozpočtu

Record the documents the estimate rests on and the class of the ladder they put it in, together with what is included and excluded, the market conditions assumed and the reason for the contingency carried. Name the design allowance the class expects, and do not state an accuracy range.

Proč: The class is a statement about the documents rather than about the estimator, which is exactly why it is worth writing down. It tells the reader whether they are looking at a number to plan around or a number to commit to, and that is the difference between an estimate that gets superseded and one that gets blamed.

VstupDesign documents at this stageAssumptions and exclusionsVýstupBasis document stating the classDesign allowance declared
2

Carry design allowance and risk as separate lines

Rezervy a nepředvídané náklady

Carry the design allowance for the class as its own line, carry the allowance for identified risks as a second one, and write the reason for each beside it rather than in a covering note.

Proč: The two answer different questions and only one of them shrinks as drawings arrive. Rolled into a single contingency, the design maturing forces you either to cut a number you should keep or to keep one you should cut, and neither version can be explained to the client without explaining the mistake.

VstupClass and its design allowanceIdentified project risksVýstupTwo allowance lines with reasonsA design allowance that can shrink
3

Roll the cost up by element as well as by trade

Rozpočet

Summarise the same cost by building element, so substructure, structure, envelope, internal finishes, services and external works each carry a total and a cost per square metre alongside the trade breakdown.

Proč: A client comparing this scheme against the last one compares elements, because trades shift with the procurement route and elements do not. It is also the fastest way to find the line that is wrong: an envelope rate out by a third is invisible in a trade total and obvious per square metre.

VstupPriced bill by tradeGross floor areaVýstupElemental summaryCost per square metre by element
4

Escalate to the mid-point of construction

Cenový index

Apply escalation from a dated index series between the date the prices were built and the mid-point of the construction period, and state both dates on the face of the estimate.

Proč: Escalating to the tender date underprices everything that happens after it and escalating to completion overprices half the job. The mid-point is where the average dollar is actually spent, and a reviewer expects to see it, so using it is one fewer thing you have to defend.

VstupBase date of the pricesConstruction start and finishVýstupEscalation to the mid-pointBoth dates stated on the estimate
5

Compare the classes and say what moved the number

Reporty

Report the newer estimate against the earlier one element by element, separating what moved because the design changed, what moved because the market moved, and what moved because an allowance was released.

Proč: When a Class B replaces a Class C the client asks one question, which is why the number changed. An answer split into design, market and allowance is a conversation about the project. A single variance figure is an accusation looking for somebody to attach itself to.

VstupThe earlier estimateThe current estimateVýstupVariance split by causeA movement the client can accept
Moduly

Moduly v tomto playbooku

5 / 190 modulů platformy

The market this case is written for

Kanada

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Více v kategorii Rozpočtování a náklady

Rozpočtování a náklady

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 kroků12 minOtevřít
Rozpočtování a náklady

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 kroků11 minOtevřít