केस / आकलन और लागत
आकलन और लागत

अनुमान को Class D से Class A तक चलाएं

बताएं कि हर अनुमान किससे तैयार हुआ और यह सीढ़ी के किस क्लास में आता है, वह design allowance जो क्लास मांगता है उसे जोखिम से अलग ढोएं, लागत को ट्रेड के साथ-साथ एलिमेंट के हिसाब से भी जोड़ें, और काम खत्म होने के दिन के बजाय निर्माण के मध्य-बिंदु तक escalate करें।

5 चरण20 मिनटलागत परामर्श / QS फर्मडेवलपर / क्लाइंटप्रोजेक्ट / निर्माण प्रबंधन फर्ममुख्य ठेकेदार

यह कैसे काम करता है, चरण दर चरण

प्लेटफ़ॉर्म भर में 5 चरण - हर एक में आप क्या करते हैं और यह क्यों मायने रखता है।

1

Say what this estimate was prepared from

अनुमान का आधार

Record the documents the estimate rests on and the class of the ladder they put it in, together with what is included and excluded, the market conditions assumed and the reason for the contingency carried. Name the design allowance the class expects, and do not state an accuracy range.

क्यों: The class is a statement about the documents rather than about the estimator, which is exactly why it is worth writing down. It tells the reader whether they are looking at a number to plan around or a number to commit to, and that is the difference between an estimate that gets superseded and one that gets blamed.

इनपुटDesign documents at this stageAssumptions and exclusionsपरिणामBasis document stating the classDesign allowance declared
2

Carry design allowance and risk as separate lines

भत्ते और आकस्मिकता

Carry the design allowance for the class as its own line, carry the allowance for identified risks as a second one, and write the reason for each beside it rather than in a covering note.

क्यों: The two answer different questions and only one of them shrinks as drawings arrive. Rolled into a single contingency, the design maturing forces you either to cut a number you should keep or to keep one you should cut, and neither version can be explained to the client without explaining the mistake.

इनपुटClass and its design allowanceIdentified project risksपरिणामTwo allowance lines with reasonsA design allowance that can shrink
3

Roll the cost up by element as well as by trade

मात्रा विवरण

Summarise the same cost by building element, so substructure, structure, envelope, internal finishes, services and external works each carry a total and a cost per square metre alongside the trade breakdown.

क्यों: A client comparing this scheme against the last one compares elements, because trades shift with the procurement route and elements do not. It is also the fastest way to find the line that is wrong: an envelope rate out by a third is invisible in a trade total and obvious per square metre.

इनपुटPriced bill by tradeGross floor areaपरिणामElemental summaryCost per square metre by element
4

Escalate to the mid-point of construction

मूल्य सूचकांक

Apply escalation from a dated index series between the date the prices were built and the mid-point of the construction period, and state both dates on the face of the estimate.

क्यों: Escalating to the tender date underprices everything that happens after it and escalating to completion overprices half the job. The mid-point is where the average dollar is actually spent, and a reviewer expects to see it, so using it is one fewer thing you have to defend.

इनपुटBase date of the pricesConstruction start and finishपरिणामEscalation to the mid-pointBoth dates stated on the estimate
5

Compare the classes and say what moved the number

रिपोर्ट

Report the newer estimate against the earlier one element by element, separating what moved because the design changed, what moved because the market moved, and what moved because an allowance was released.

क्यों: When a Class B replaces a Class C the client asks one question, which is why the number changed. An answer split into design, market and allowance is a conversation about the project. A single variance figure is an accusation looking for somebody to attach itself to.

इनपुटThe earlier estimateThe current estimateपरिणामVariance split by causeA movement the client can accept
मॉड्यूल

इस प्लेबुक के मॉड्यूल

प्लेटफ़ॉर्म के 190 में से 5 मॉड्यूल

The market this case is written for

कनाडा

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

आकलन और लागत में और देखें

आकलन और लागत

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 चरण8 मिनटखोलें
आकलन और लागत

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 चरण12 मिनटखोलें
आकलन और लागत

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 चरण11 मिनटखोलें