Vakalar / Keşif ve maliyet
Keşif ve maliyet

Tahmini Class D'den Class A'ya yürütün

Her tahminin neden hazırlandığını ve bunun onu merdivenin hangi sınıfına koyduğunu söyleyin, sınıfın beklediği tasarım payını riskten ayrı taşıyın, maliyeti işkoluna göre olduğu kadar elemana göre de toplayın, ve işin bittiği güne değil yapımın orta noktasına göre eskale edin.

5 adım20 dkMaliyet danışmanlığı / QSGeliştirici / işverenProje / inşaat yönetim bürosuAna yüklenici

Nasıl çalışır, adım adım

Platform genelinde 5 adım - her birinde ne yapacağınız ve neden önemli olduğu.

1

Say what this estimate was prepared from

Tahmin Esası

Record the documents the estimate rests on and the class of the ladder they put it in, together with what is included and excluded, the market conditions assumed and the reason for the contingency carried. Name the design allowance the class expects, and do not state an accuracy range.

Neden: The class is a statement about the documents rather than about the estimator, which is exactly why it is worth writing down. It tells the reader whether they are looking at a number to plan around or a number to commit to, and that is the difference between an estimate that gets superseded and one that gets blamed.

GirdiDesign documents at this stageAssumptions and exclusionsÇıktıBasis document stating the classDesign allowance declared
2

Carry design allowance and risk as separate lines

Ödenekler ve Beklenmedik Giderler

Carry the design allowance for the class as its own line, carry the allowance for identified risks as a second one, and write the reason for each beside it rather than in a covering note.

Neden: The two answer different questions and only one of them shrinks as drawings arrive. Rolled into a single contingency, the design maturing forces you either to cut a number you should keep or to keep one you should cut, and neither version can be explained to the client without explaining the mistake.

GirdiClass and its design allowanceIdentified project risksÇıktıTwo allowance lines with reasonsA design allowance that can shrink
3

Roll the cost up by element as well as by trade

Keşif Özeti

Summarise the same cost by building element, so substructure, structure, envelope, internal finishes, services and external works each carry a total and a cost per square metre alongside the trade breakdown.

Neden: A client comparing this scheme against the last one compares elements, because trades shift with the procurement route and elements do not. It is also the fastest way to find the line that is wrong: an envelope rate out by a third is invisible in a trade total and obvious per square metre.

GirdiPriced bill by tradeGross floor areaÇıktıElemental summaryCost per square metre by element
4

Escalate to the mid-point of construction

Fiyat Endeksi

Apply escalation from a dated index series between the date the prices were built and the mid-point of the construction period, and state both dates on the face of the estimate.

Neden: Escalating to the tender date underprices everything that happens after it and escalating to completion overprices half the job. The mid-point is where the average dollar is actually spent, and a reviewer expects to see it, so using it is one fewer thing you have to defend.

GirdiBase date of the pricesConstruction start and finishÇıktıEscalation to the mid-pointBoth dates stated on the estimate
5

Compare the classes and say what moved the number

Raporlar

Report the newer estimate against the earlier one element by element, separating what moved because the design changed, what moved because the market moved, and what moved because an allowance was released.

Neden: When a Class B replaces a Class C the client asks one question, which is why the number changed. An answer split into design, market and allowance is a conversation about the project. A single variance figure is an accusation looking for somebody to attach itself to.

GirdiThe earlier estimateThe current estimateÇıktıVariance split by causeA movement the client can accept
Modüller

Bu senaryodaki modüller

5 / 190 platform modülü

The market this case is written for

Kanada

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Keşif ve maliyet kategorisinde daha fazlası

Keşif ve maliyet

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 adım12 dk
Keşif ve maliyet

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 adım11 dk