Escalate an estimate with price indices

Bring base-date rates forward to the midpoint of construction using published cost indices, so the number reflects when the money is really spent rather than the day the rate was set.

4 koraka9 minKonzultant za troškove / QSGlavni izvođačInvestitor / naručitelj

Kako funkcionira, korak po korak

4 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Set base and target dates

Indeks cijena

Fix the base date of your rates and the target date to escalate to, usually the midpoint of the construction period where spend is heaviest.

Zašto: Escalating to the midpoint rather than the start or the end is the fair average across the spend curve. Getting these two dates right is most of the accuracy of the whole exercise.

UlazBase-date estimateConstruction datesRezultatBase and target dates
2

Read the escalation factor

Indeks cijena

Pick the index series that best matches the work - building, civils, or a trade-specific one - and read the factor between the base and target dates.

Zašto: The right series matters: labour, steel and energy do not move together. Choosing an index that fits the work is what makes the escalation credible rather than a blanket guess.

UlazBase and target datesPublished index seriesRezultatEscalation factor
3

Apply it to the bill

Troškovnik

Apply the factor to the bill and read the escalated total next to the base figure, so the uplift is a line you can point at rather than a number folded into the rates.

Zašto: Showing the base and the escalated total side by side keeps the client's trust. It also lets you re-run the uplift cleanly if the start date slips again.

UlazEscalation factorBase-date billRezultatEscalated total
4

Record it in the basis

Osnova procjene

Write the base date, the index series and the factor into the basis of estimate so anyone reading the price later knows exactly how it was escalated.

Zašto: An escalation nobody can reconstruct is an escalation nobody trusts. Recording the working is what turns a defensible method into an auditable one.

UlazEscalated totalRezultatRecorded basis