Escalate an estimate with price indices
Bring base-date rates forward to the midpoint of construction using published cost indices, so the number reflects when the money is really spent rather than the day the rate was set.
Kako funkcionira, korak po korak
4 koraka kroz platformu - što radite u svakom i zašto je važno.
Set base and target dates
Indeks cijenaFix the base date of your rates and the target date to escalate to, usually the midpoint of the construction period where spend is heaviest.
Zašto: Escalating to the midpoint rather than the start or the end is the fair average across the spend curve. Getting these two dates right is most of the accuracy of the whole exercise.
Read the escalation factor
Indeks cijenaPick the index series that best matches the work - building, civils, or a trade-specific one - and read the factor between the base and target dates.
Zašto: The right series matters: labour, steel and energy do not move together. Choosing an index that fits the work is what makes the escalation credible rather than a blanket guess.
Apply it to the bill
TroškovnikApply the factor to the bill and read the escalated total next to the base figure, so the uplift is a line you can point at rather than a number folded into the rates.
Zašto: Showing the base and the escalated total side by side keeps the client's trust. It also lets you re-run the uplift cleanly if the start date slips again.
Record it in the basis
Osnova procjeneWrite the base date, the index series and the factor into the basis of estimate so anyone reading the price later knows exactly how it was escalated.
Zašto: An escalation nobody can reconstruct is an escalation nobody trusts. Recording the working is what turns a defensible method into an auditable one.