Escalate an estimate with price indices

Bring base-date rates forward to the midpoint of construction using published cost indices, so the number reflects when the money is really spent rather than the day the rate was set.

Шагов: 49 минСметный консультант / QSГенеральный подрядчикДевелопер / заказчик

Как это работает, шаг за шагом

4 шагов через всю платформу - что делать на каждом и почему это важно.

1

Set base and target dates

Индекс цен

Fix the base date of your rates and the target date to escalate to, usually the midpoint of the construction period where spend is heaviest.

Зачем: Escalating to the midpoint rather than the start or the end is the fair average across the spend curve. Getting these two dates right is most of the accuracy of the whole exercise.

На входеBase-date estimateConstruction datesНа выходеBase and target dates
2

Read the escalation factor

Индекс цен

Pick the index series that best matches the work - building, civils, or a trade-specific one - and read the factor between the base and target dates.

Зачем: The right series matters: labour, steel and energy do not move together. Choosing an index that fits the work is what makes the escalation credible rather than a blanket guess.

На входеBase and target datesPublished index seriesНа выходеEscalation factor
3

Apply it to the bill

Ведомость объёмов работ

Apply the factor to the bill and read the escalated total next to the base figure, so the uplift is a line you can point at rather than a number folded into the rates.

Зачем: Showing the base and the escalated total side by side keeps the client's trust. It also lets you re-run the uplift cleanly if the start date slips again.

На входеEscalation factorBase-date billНа выходеEscalated total
4

Record it in the basis

Обоснование сметы

Write the base date, the index series and the factor into the basis of estimate so anyone reading the price later knows exactly how it was escalated.

Зачем: An escalation nobody can reconstruct is an escalation nobody trusts. Recording the working is what turns a defensible method into an auditable one.

На входеEscalated totalНа выходеRecorded basis