Run the site day
Close the day out properly: record the diary, book the labour and plant hours, upload the p…
Register a new drawing revision, mark the old one superseded, transmit it to every trade that builds from it, and confirm the current sheet is the one on the wall at the workface.
3 steps across the platform - what you do at each one, and why it matters.
Load the new revision into the document register with its number, date and revision letter, mark the previous version superseded, and note what changed so a reader knows why it moved.
Why: Two live copies of the same drawing is how a wall gets built to last month geometry. One controlled register, with the old revision plainly retired, is what leaves no doubt which sheet is the truth.
Send a transmittal to every trade and subcontractor working off that drawing, listing the revision issued and the date, and keep the record of who it went to and when.
Why: A revision that sits in the register but never reaches the gang who pours the slab has changed nothing. The transmittal record is also your proof that the trade had the current information when they built it.
On the walk, check the drawings pinned up at the work area and in the trade cabins carry the latest revision, and pull down every superseded sheet you find still in use.
Why: A superseded drawing left on the wall keeps building the old detail no matter how clean your register is. Clearing it at the source is the cheapest defect you will ever prevent.
3 / 184 platform modules
Close the day out properly: record the diary, book the labour and plant hours, upload the p…
Turn a question from the working face into a tracked request, drive it to the party who own…
Turn instructed extra work into a claim that gets paid: record the labour, plant and materi…