Clear the snag list before handover

Drive the defects to zero before you hand over: work the open snags, re-inspect the fixes, and only sign the closeout when the list is genuinely clear.

3단계8 분종합건설사PM/CM 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 3단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Work the open snags down

펀치 리스트

Go through the punch list, make sure every open snag is assigned to the trade that owns it with a date to fix by, and chase the ones blocking handover to the front of the queue.

이유: A snag with no owner and no date is a snag that does not get fixed. Assigning and dating each one is what turns a stale list into work that actually closes before the handover date.

입력Open snag listResponsible trades결과Assigned defectsTarget close dates
2

Re-inspect the fixes

검사

Inspect each snag the trade says is done, close the ones that genuinely pass and reopen the ones that do not, with a photo either way, so closed means checked.

이유: A snag closed on the trade's word alone is the one the client finds on their walk-round. A quick re-inspection is what keeps the list honest and stops handover slipping when the client rejects a half-done fix.

입력Reported fixesSnag details결과Verified closuresReopened defects
3

Sign off on a clean list

인계 및 준공 정산

With the snags verified clear, complete the closeout checklist and record the sign-off, so handover proceeds on evidence that the defects are actually done, not on a promise to finish later.

이유: Handing over on a promise to close snags later is how a defects list becomes a dispute. Gating closeout on a clean, verified list is what protects your retention and your reputation with the client.

입력Verified closuresHandover checklist결과Closeout sign-offHandover clearance