Lepi kokku verstapostid, esita arved nende valmimisel, ning lase objekti reguleerival õigeaegse makse seadusel käivitada kell, nii et hilinenud maksel on kuupäev, summa ja intressinumber, mitte vaidlus.

5 sammu16 minPeatöövõtjaErialaalltöövõtjaArendaja / klient

Kuidas see töötab, samm-sammult

5 sammu läbi platvormi - mida teete igas ja miks see loeb.

1

Write the payment schedule into the contract

Lepingud

Record the contract with its price, its payment terms and the milestones that trigger a payment, so what is owed and when is a property of the job rather than a thing two people recall differently.

Ekraanipilt, samm 1: Write the payment schedule into the contract (Lepingud, Saa õigel ajal makse erasektori objektil)
Lepingud: Write the payment schedule into the contract

Miks: A milestone that was never written down cannot be billed without a discussion, and the discussion always happens when you need the money. Written up front, the same milestone is an invoice trigger nobody has to justify.

SisendScope and agreed priceMilestones both sides acceptVäljundContract with a payment schedulePayment terms recorded, not remembered
2

Bill the milestone the day it completes

Lepingud

Raise the payment claim against the milestone as it completes, with the date it went out. Billing late shortens nothing except your own runway, and the submission date is what every subsequent question turns on.

Ekraanipilt, samm 2: Bill the milestone the day it completes (Lepingud, Saa õigel ajal makse erasektori objektil)
Lepingud: Bill the milestone the day it completes

Miks: The statutory clock starts from an event, and on private work that event is usually your claim arriving. A claim you sat on for two weeks is two weeks of interest you will never see, and it is the one part of the timeline entirely within your control.

SisendWork actually completeEvidence it is completeVäljundA payment claim for the milestoneThe date it was submitted
3

Run the clock the law actually gives you

Maksekell

Pick the prompt payment regime that governs this job, by state and by whether the work is public or private, and start the clock from the claim. The due date is then computed from the statute rather than assumed from habit.

Miks: The periods are genuinely different between states and between public and private work, which is exactly why people guess and guess wrong. Naming the regime turns the due date into something checkable, and it means the same job billed in another state does not quietly inherit the wrong deadline.

SisendState and whether the work is publicThe date the claim went inVäljundThe date payment becomes dueThe regime that governs, named
4

Let the overdue amount price itself

Maksekell

Once the due date passes, the interest the regime provides accrues on the unpaid amount and is calculated rather than estimated, so a reminder can carry a figure instead of a complaint.

Miks: Asking to be paid is awkward and easy to defer. Sending a number that grows on a schedule the law set is neither, and it changes what the other side is deciding: not whether to be fair to you, but whether delay is now costing them more than paying.

SisendDue date passedAmount still unpaidVäljundInterest computed from the statuteA position you can put in writing
5

See who actually pays you late

Finants

Reconcile what was billed against what arrived, and keep the ageing rather than clearing it from memory once the money lands.

Ekraanipilt, samm 5: See who actually pays you late (Finants, Saa õigel ajal makse erasektori objektil)
Finants: See who actually pays you late

Miks: A client who pays a month late every time is a financing cost you are carrying without pricing it. Once that is visible per client rather than felt in general, it becomes something you can price into the next bid or decline.

SisendPayments receivedClaims raised to dateVäljundWhat is still owed, by ageWho pays late, on the record
Moodulid

Selle tegevusjuhendi moodulid

3 / 190 platvormi moodulit

The market this case is written for

Ameerika Ühendriigid

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CSI MasterFormat
  • UniFormat II
  • AIA A201

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Rohkem valdkonnas Äritegevus ja lepingud

Äritegevus ja lepingud

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 sammu11 minAva