سناریوها / برآورد و هزینه‌یابی
برآورد و هزینه‌یابی

ساخت نرخ واحد جامع بر اساس GB 50500

یک قلم کدگذاری‌شده در فهرست مقادیر بردارید، نیروی کار، مصالح و ماشین‌آلات خودتان را پشت آن قرار دهید، هزینه مدیریت و سود را اضافه کنید، و نرخ واحد جامعی بخوانید که اجزای آن با عدد آن ردیف جمع می‌شود.

5 مرحله14 دقیقهپیمانکار عمومیپیمانکار جزء تخصصیمشاوره هزینه / QS

چگونه کار می‌کند، گام به گام

5 گام در سراسر پلتفرم - کاری که در هر گام انجام می‌دهید و چرا اهمیت دارد.

1

Open the coded bill and pick the item

صورت مقادیر (BOQ)

Open the bill, find the section and the item you are pricing, and read the item description and its code before you price anything. The code tells you which schedule item this is; the description tells you what the rate has to cover.

چرا: Under GB 50500 the item description is the ground for what the rate includes, and most final-account arguments start with an item whose description did not say enough. Reading it before you price is the cheapest minute in the whole exercise.

ورودیBill of quantitiesGB 50500 item codesخروجیThe item you are pricing
2

Hold your labour, material and plant rates in one place

کاتالوگ منبع

Put the prices you actually buy at into the resource catalog: wage costs by trade, material prices by supplier, plant by the hour. Keep them current rather than accurate once a year.

چرا: The rates a contractor is judged on are the firm's own, and a published average is a starting point rather than an answer. Holding them centrally means the next hundred rates you build are consistent with this one, and a price change is one edit instead of a hunt through old bids.

ورودیYour own supplier pricesCrew and plant costsخروجیMaintained resource rates
3

Compose the rate and read the analysis back

صورت مقادیر (BOQ)

Enter the labour, material and plant the item consumes per unit, then open the rate analysis on the line. It shows the direct cost per unit, the management fee, the profit, the comprehensive unit rate and the item total, in that order.

چرا: That sequence is the composition GB 50500 defines, and seeing it as a chain rather than as a total is what lets you answer a client who asks why the rate is what it is. The fee and the profit are taken on the direct cost, so the measure items, the statutory charges and the tax stay where they belong, on the bill total, instead of inflating a rate from the inside.

ورودیThe coded itemLabour, material and plant ratesخروجیDirect cost per unitComprehensive unit rate
4

Validate before the bill leaves your desk

اعتبارسنجی

Run the bill through validation. For a project in China the GB 50500 rules are selected for you: every item has to carry a code, and the code has to be well formed at nine or twelve digits.

چرا: One item left at zero can carry a loss all the way to site, and a malformed code is the sort of thing an owner's reviewer finds before you do. The check is on the shape of the code rather than on its membership in the national schedule, so treat a clean run as a floor and still read the codes yourself.

ورودیPriced billخروجیValidation reportItems left at zero
5

Issue the priced bill with its working behind it

گزارش‌ها

Report the priced bill, and keep the rate analysis for the items that carry real money. The analysis is the document you bring to a rate query, not something you rebuild when one arrives.

چرا: A rate you can take apart in a meeting settles a query in ten minutes. A rate that exists only as a total turns the same query into a week of reconstruction, and every reconstruction after the event looks like an argument rather than a record.

ورودیValidated priced billخروجیPriced bill for issueRate analysis behind each item
ماژول‌ها

ماژول‌های این سناریو

4 / 190 ماژول پلتفرم

The market this case is written for

چین

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

بیشتر در برآورد و هزینه‌یابی

برآورد و هزینه‌یابی

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 مرحله8 دقیقهباز کردن
برآورد و هزینه‌یابی

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 مرحله12 دقیقهباز کردن
برآورد و هزینه‌یابی

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 مرحله11 دقیقهباز کردن