תרחישים / אומדן ותמחור
אומדן ותמחור

בניית מחיר יחידה מקיף לפי GB 50500

קחו סעיף מקודד בכתב הכמויות, הציבו מאחוריו את העבודה, החומר והציוד שלכם, הוסיפו את דמי הניהול והרווח, וקראו מחיר יחידה מקיף שחלקיו מסתכמים במספר שבשורה.

5 שלבים14 דק׳קבלן ראשיקבלן משנה מתמחהייעוץ עלויות / כמויות

איך זה עובד, שלב אחר שלב

5 שלבים לאורך הפלטפורמה - מה עושים בכל שלב ולמה זה חשוב.

1

Open the coded bill and pick the item

כתב כמויות

Open the bill, find the section and the item you are pricing, and read the item description and its code before you price anything. The code tells you which schedule item this is; the description tells you what the rate has to cover.

למה: Under GB 50500 the item description is the ground for what the rate includes, and most final-account arguments start with an item whose description did not say enough. Reading it before you price is the cheapest minute in the whole exercise.

נכנסBill of quantitiesGB 50500 item codesיוצאThe item you are pricing
2

Hold your labour, material and plant rates in one place

קטלוג משאבים

Put the prices you actually buy at into the resource catalog: wage costs by trade, material prices by supplier, plant by the hour. Keep them current rather than accurate once a year.

למה: The rates a contractor is judged on are the firm's own, and a published average is a starting point rather than an answer. Holding them centrally means the next hundred rates you build are consistent with this one, and a price change is one edit instead of a hunt through old bids.

נכנסYour own supplier pricesCrew and plant costsיוצאMaintained resource rates
3

Compose the rate and read the analysis back

כתב כמויות

Enter the labour, material and plant the item consumes per unit, then open the rate analysis on the line. It shows the direct cost per unit, the management fee, the profit, the comprehensive unit rate and the item total, in that order.

למה: That sequence is the composition GB 50500 defines, and seeing it as a chain rather than as a total is what lets you answer a client who asks why the rate is what it is. The fee and the profit are taken on the direct cost, so the measure items, the statutory charges and the tax stay where they belong, on the bill total, instead of inflating a rate from the inside.

נכנסThe coded itemLabour, material and plant ratesיוצאDirect cost per unitComprehensive unit rate
4

Validate before the bill leaves your desk

אימות

Run the bill through validation. For a project in China the GB 50500 rules are selected for you: every item has to carry a code, and the code has to be well formed at nine or twelve digits.

למה: One item left at zero can carry a loss all the way to site, and a malformed code is the sort of thing an owner's reviewer finds before you do. The check is on the shape of the code rather than on its membership in the national schedule, so treat a clean run as a floor and still read the codes yourself.

נכנסPriced billיוצאValidation reportItems left at zero
5

Issue the priced bill with its working behind it

דוחות

Report the priced bill, and keep the rate analysis for the items that carry real money. The analysis is the document you bring to a rate query, not something you rebuild when one arrives.

למה: A rate you can take apart in a meeting settles a query in ten minutes. A rate that exists only as a total turns the same query into a week of reconstruction, and every reconstruction after the event looks like an argument rather than a record.

נכנסValidated priced billיוצאPriced bill for issueRate analysis behind each item
מודולים

המודולים בתרחיש הזה

4 מתוך 190 מודולי הפלטפורמה

The market this case is written for

סין

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

עוד ב-אומדן ותמחור

אומדן ותמחור

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 שלבים8 דק׳פתיחה
אומדן ותמחור

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 שלבים12 דק׳פתיחה
אומדן ותמחור

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 שלבים11 דק׳פתיחה