Run a tender from a BOQ
Take a priced bill of quantities out to market: package it, invite the subcontractors, leve…
Izjednačite ponude za paket na jedan opseg, provjerite dokumente predviđenog pobjednika na dan kad namjeravate dodijeliti posao, pustite da dodjela pričeka umjesto da prođe kad je dokument istekao, i napišite podugovor s pridržajem i uvjetima plaćanja preuzetim iz nadređenog ugovora.
6 koraka kroz platformu - što radite u svakom i zašto je važno.
Set the bids for the package side by side against the scope they were invited on, bring every exclusion and alternate onto the face of the comparison, and carry a price for each gap so the totals compare complete scopes.

Zašto: Five bids that are each a single number look comparable and are not. The one that excluded the hoisting and the one that carried the permit have answered different questions, and the difference does not surface until it arrives as a change order in the autumn with no competitive tension left in it.
Keep the insurance certificate and the other documents the package requires on each subcontractor's record with the date it expires, and file the document itself rather than a note saying it was seen.

Zašto: A register of documents without their expiry dates cannot answer the only question anybody ever asks it, which is whether the cover was in place on a particular day. Recording the expiry is the whole difference between a filing cabinet and a check.
Before writing the award, check the intended winner's required documents as at the date you intend to award. Where one has lapsed the award waits, and what goes back to the subcontractor names the document and the day it lapsed rather than saying they are blocked.
Zašto: The honest statement is that a document was valid on the award date, and not that compliance is established for the contract or for the duration of the work, which is a different claim nobody has checked. A gate that can be waved through is worse than no gate at all, because everybody downstream believes it.
Load the renewed certificate against the same document type on the record, keeping the lapsed one in the history rather than replacing it, and run the same check on the same award date.

Zašto: Nothing should be overridden here; the underlying fact should change. Keeping the lapsed certificate beside the renewed one is also what lets you answer, a year later, what cover was actually in place during the week the work started.
Turn the levelled scope into the subcontract, taking the holdback percentage and the payment terms from the contract above rather than typing them again, so the 10 percent held below matches the 10 percent held above and the dates line up.

Zašto: The scope that was levelled is the scope that has to be bought, and a subcontract retyped from a bid letter quietly drops the exclusions levelling had just made visible. Terms that do not match the contract above are also how a general contractor ends up owing money on a date it has not itself been paid on.
Issue the recommendation with the adjusted total for each bidder, the reason the winner was chosen, the check that was run and the date it was run as at, and compare the committed value against the estimate line it came from.

Zašto: On public and institutional work the reasoning gets read by somebody who was not in the room, sometimes after a protest. Writing it while the comparison is still in front of you takes minutes, and the buyout comparison tells you the result package by package while there is still a job left to act on it.
4 / 190 modula platforme
Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.
Standards it follows
You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.
Take a priced bill of quantities out to market: package it, invite the subcontractors, leve…
Buy the quantities you already priced: raise a requisition off the bill, place the order wi…
Take a folder of returned tenders that never quite match, strip them back to the same scope…