Run a tender from a BOQ
Take a priced bill of quantities out to market: package it, invite the subcontractors, leve…
Level the bids for a package onto one scope, check the intended winner's documents as at the day you mean to award, let the award wait rather than be waved through when one has lapsed, and write the subcontract with the holdback and payment terms taken from the contract above.
6 steps across the platform - what you do at each one, and why it matters.
Set the bids for the package side by side against the scope they were invited on, bring every exclusion and alternate onto the face of the comparison, and carry a price for each gap so the totals compare complete scopes.
Why: Five bids that are each a single number look comparable and are not. The one that excluded the hoisting and the one that carried the permit have answered different questions, and the difference does not surface until it arrives as a change order in the autumn with no competitive tension left in it.
Keep the insurance certificate and the other documents the package requires on each subcontractor's record with the date it expires, and file the document itself rather than a note saying it was seen.
Why: A register of documents without their expiry dates cannot answer the only question anybody ever asks it, which is whether the cover was in place on a particular day. Recording the expiry is the whole difference between a filing cabinet and a check.
Before writing the award, check the intended winner's required documents as at the date you intend to award. Where one has lapsed the award waits, and what goes back to the subcontractor names the document and the day it lapsed rather than saying they are blocked.
Why: The honest statement is that a document was valid on the award date, and not that compliance is established for the contract or for the duration of the work, which is a different claim nobody has checked. A gate that can be waved through is worse than no gate at all, because everybody downstream believes it.
Load the renewed certificate against the same document type on the record, keeping the lapsed one in the history rather than replacing it, and run the same check on the same award date.
Why: Nothing should be overridden here; the underlying fact should change. Keeping the lapsed certificate beside the renewed one is also what lets you answer, a year later, what cover was actually in place during the week the work started.
Turn the levelled scope into the subcontract, taking the holdback percentage and the payment terms from the contract above rather than typing them again, so the 10 percent held below matches the 10 percent held above and the dates line up.
Why: The scope that was levelled is the scope that has to be bought, and a subcontract retyped from a bid letter quietly drops the exclusions levelling had just made visible. Terms that do not match the contract above are also how a general contractor ends up owing money on a date it has not itself been paid on.
Issue the recommendation with the adjusted total for each bidder, the reason the winner was chosen, the check that was run and the date it was run as at, and compare the committed value against the estimate line it came from.
Why: On public and institutional work the reasoning gets read by somebody who was not in the room, sometimes after a protest. Writing it while the comparison is still in front of you takes minutes, and the buyout comparison tells you the result package by package while there is still a job left to act on it.
Take a priced bill of quantities out to market: package it, invite the subcontractors, leve…
Buy the quantities you already priced: raise a requisition off the bill, place the order wi…
Take a folder of returned tenders that never quite match, strip them back to the same scope…