Balance crews and plant across the programme

Read the labour and plant the near-term programme actually needs, check it against what is booked on site, and close the gap before a task stalls for want of a hand or a machine.

3 steps10 minProject / construction managerGeneral contractorSpecialist subcontractor

How it works, step by step

3 steps across the platform - what you do at each one, and why it matters.

1

Read the near-term demand

Advanced scheduling

Look at the next few weeks of activities on the programme and note the trade, crew size and any plant each one needs to run to plan.

Why: A task with no crew or crane booked against it is a task that will not start on the day the programme says it will.

InProject programmeLookahead windowOutCrew and plant demandTrade-by-trade needs
2

Check what is actually booked

Field time

Compare the hours and plant booked in the field against what the lookahead calls for, and flag the trades running short before the week begins.

Why: Booked hours are the ground truth of what will really turn up on site. Catching a shortfall a week out is a phone call; catching it on the day is a stalled gang.

InCrew and plant demandBooked field hoursPlant bookingsOutResource shortfall listFlagged short trades
3

Close the gap and report it

Reports

Arrange the extra crew, plant or overtime needed to cover the gap, and report the resourced lookahead so the wider team can see the plan is properly resourced, not just dated.

Why: A lookahead with dates but no resourcing behind it is a wish list. Showing it is resourced is what makes the plan believable to the trades who have to deliver it.

InResource shortfall listAvailable crews and plantOutResourced lookaheadResourcing report