Cerrar desde la substantial performance hasta el finiquito

Certifica y fecha la substantial performance una sola vez, pon en un solo registro cada consecuencia que se deriva de ella, cotiza la lista de deficiencias para que la reserva sea dinero y no una lista de pendientes, y concilia un finiquito donde cada línea se pueda rastrear hacia atrás.

6 pasos22 minContratista generalGestora de proyectos / construcciónConsultoría de costos / QS

Cómo funciona, paso a paso

6 pasos a lo largo de la plataforma - qué haces en cada uno y por qué importa.

1

Certify the date once, and only once

Control de obra

Record substantial performance as a dated, certified event with the signature behind it, and attach the certificate together with the record of the state of the work it was certified against.

Por que: Everything downstream counts from this date, so it has to be one date with a document behind it rather than a date three people remember slightly differently. The version that ends up challenged is always the one nobody can produce on the day it is questioned.

EntradaState of the workConsultant certificationResultadoCertified date on recordThe evidence it rests on
2

Put every consequence on one register

Plazos

Enter the obligations that run from the certified date against it: publication of the notice, the period in which security can still be claimed, the holdback release, and the date deficiencies are reckoned from. Count each one on the rules of the province the work is in.

Por que: Four consequences tracked in four places are four chances to miss one, and the one that gets missed is always the one with no invoice attached to remind you. A single register in date order is also what lets somebody cover for you without being briefed.

EntradaThe certified dateThe provincial rules that applyResultadoEvery consequence datedOne register instead of four
3

Price the deficiency list so the reserve is money

Lista de pendientes

Value each outstanding item at what it will cost to complete or correct, and total the list as the reserve to be held against release rather than reporting it as a count of open items.

Por que: A deficiency list is a claim about money and a checklist is a claim about tidiness. Releasing against a count treats ninety small items and one expensive one as ninety-one, and the expensive one is the entire reason the release is being argued about.

EntradaOutstanding and defective workRates to complete or correctResultadoPriced deficiency listA reserve with a number on it
4

Release the holdback less the reserve, and record it

Contratos

Record the release against the contract for the holdback balance less the valued deficiency reserve, so the ledger shows what was held, what was released, on what date, and against what.

Por que: The release is the moment a balance and a recomputed percentage stop being the same number, and only writing the release down as a transaction keeps them together. A release nobody recorded is one both sides will later compute differently and each be certain about.

EntradaHoldback balancePriced deficiency reserveResultadoRelease recorded with its dateA balance that still reconciles
5

Reconcile the final account line by line

Finanzas

Build the final account from the original contract price, every approved change with its code, holdback released, deficiency deductions and any credits, so that each line points at the transaction that produced it.

Por que: A final account is agreed when the other side can check it, not when it is delivered. One that can be walked backwards to its transactions settles in a meeting; one that arrives as a total settles in a negotiation, and the negotiation is where the last few percent of the job goes.

EntradaContract price, changes, releases, deductionsResultadoFinal account, every line traceableA figure that can be walked back
6

Issue the closeout package and keep the file copy

Informes

Issue the final account together with the certified date, the deficiency list and its status, the holdback release and the warranties, as one package to the client and one record to your own file.

Por que: The package is what the client's finance department needs before it can pay, and the file copy is what you need when a security claim or a deficiency argument arrives eighteen months later, by which time everyone who did the work has moved to another job.

EntradaFinal account and supporting recordsResultadoCloseout package issuedA file that survives the team
Módulos

Módulos de este playbook

6 / 190 módulos de la plataforma

The market this case is written for

Canadá

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Más en Entrega y ciclo de vida

Entrega y ciclo de vida

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 pasos14 minAbrir
Entrega y ciclo de vida

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3 pasos12 minAbrir