Казуси / Предаване и жизнен цикъл
Предаване и жизнен цикъл

Приключете от substantial performance до окончателната сметка

Сертифицирайте и датирайте substantial performance веднъж, поставете всяко произтичащо от него следствие в един регистър, остойностете списъка с недостатъци, за да е резервът пари, а не чеклиста, и съгласувайте окончателна сметка, чийто всеки ред може да се проследи назад.

6 стъпки22 минГлавен изпълнителФирма за проектен / строителен мениджмънтКонсултиране по разходи / остойностяване

Как работи, стъпка по стъпка

6 стъпки през платформата - какво правите на всяка и защо е важно.

1

Certify the date once, and only once

Контрол на строителството

Record substantial performance as a dated, certified event with the signature behind it, and attach the certificate together with the record of the state of the work it was certified against.

Защо: Everything downstream counts from this date, so it has to be one date with a document behind it rather than a date three people remember slightly differently. The version that ends up challenged is always the one nobody can produce on the day it is questioned.

ВходState of the workConsultant certificationРезултатCertified date on recordThe evidence it rests on
2

Put every consequence on one register

Крайни срокове

Enter the obligations that run from the certified date against it: publication of the notice, the period in which security can still be claimed, the holdback release, and the date deficiencies are reckoned from. Count each one on the rules of the province the work is in.

Защо: Four consequences tracked in four places are four chances to miss one, and the one that gets missed is always the one with no invoice attached to remind you. A single register in date order is also what lets somebody cover for you without being briefed.

ВходThe certified dateThe provincial rules that applyРезултатEvery consequence datedOne register instead of four
3

Price the deficiency list so the reserve is money

Списък с дефекти

Value each outstanding item at what it will cost to complete or correct, and total the list as the reserve to be held against release rather than reporting it as a count of open items.

Защо: A deficiency list is a claim about money and a checklist is a claim about tidiness. Releasing against a count treats ninety small items and one expensive one as ninety-one, and the expensive one is the entire reason the release is being argued about.

ВходOutstanding and defective workRates to complete or correctРезултатPriced deficiency listA reserve with a number on it
4

Release the holdback less the reserve, and record it

Договори

Record the release against the contract for the holdback balance less the valued deficiency reserve, so the ledger shows what was held, what was released, on what date, and against what.

Защо: The release is the moment a balance and a recomputed percentage stop being the same number, and only writing the release down as a transaction keeps them together. A release nobody recorded is one both sides will later compute differently and each be certain about.

ВходHoldback balancePriced deficiency reserveРезултатRelease recorded with its dateA balance that still reconciles
5

Reconcile the final account line by line

Финанси

Build the final account from the original contract price, every approved change with its code, holdback released, deficiency deductions and any credits, so that each line points at the transaction that produced it.

Защо: A final account is agreed when the other side can check it, not when it is delivered. One that can be walked backwards to its transactions settles in a meeting; one that arrives as a total settles in a negotiation, and the negotiation is where the last few percent of the job goes.

ВходContract price, changes, releases, deductionsРезултатFinal account, every line traceableA figure that can be walked back
6

Issue the closeout package and keep the file copy

Отчети

Issue the final account together with the certified date, the deficiency list and its status, the holdback release and the warranties, as one package to the client and one record to your own file.

Защо: The package is what the client's finance department needs before it can pay, and the file copy is what you need when a security claim or a deficiency argument arrives eighteen months later, by which time everyone who did the work has moved to another job.

ВходFinal account and supporting recordsРезултатCloseout package issuedA file that survives the team
Модули

Модули в този наръчник

6 / 190 модула на платформата

The market this case is written for

Канада

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Още в Предаване и жизнен цикъл

Предаване и жизнен цикъл

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 стъпки14 минОтвори
Предаване и жизнен цикъл

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3 стъпки12 минОтвори
Предаване и жизнен цикъл

Run a handover acceptance inspection

Walk the finished works with the client, record what passes and what does not against the a…

3 стъпки11 минОтвори