Isara mula sa substantial performance hanggang sa final account

I-certify at petsahan ang substantial performance nang isang beses, ilagay ang bawat bunga na nagmula rito sa isang rehistro, presyuhan ang listahan ng kakulangan para maging pera ang reserba sa halip na checklist lamang, at itugma ang final account na kung saan ang bawat linya ay maaaring subaybayan pabalik.

6 hakbang22 minGeneral ContractorProject / Construction Management FirmCost Consultancy / QS Practice

Paano ito gumagana, hakbang-hakbang

6 hakbang sa buong platform - ano ang gagawin mo sa bawat isa at bakit mahalaga ito.

1

Certify the date once, and only once

Kontrol sa Konstruksyon

Record substantial performance as a dated, certified event with the signature behind it, and attach the certificate together with the record of the state of the work it was certified against.

Bakit: Everything downstream counts from this date, so it has to be one date with a document behind it rather than a date three people remember slightly differently. The version that ends up challenged is always the one nobody can produce on the day it is questioned.

PapasokState of the workConsultant certificationLumalabasCertified date on recordThe evidence it rests on
2

Put every consequence on one register

Mga Deadline

Enter the obligations that run from the certified date against it: publication of the notice, the period in which security can still be claimed, the holdback release, and the date deficiencies are reckoned from. Count each one on the rules of the province the work is in.

Bakit: Four consequences tracked in four places are four chances to miss one, and the one that gets missed is always the one with no invoice attached to remind you. A single register in date order is also what lets somebody cover for you without being briefed.

PapasokThe certified dateThe provincial rules that applyLumalabasEvery consequence datedOne register instead of four
3

Price the deficiency list so the reserve is money

Listahan ng Depekto

Value each outstanding item at what it will cost to complete or correct, and total the list as the reserve to be held against release rather than reporting it as a count of open items.

Bakit: A deficiency list is a claim about money and a checklist is a claim about tidiness. Releasing against a count treats ninety small items and one expensive one as ninety-one, and the expensive one is the entire reason the release is being argued about.

PapasokOutstanding and defective workRates to complete or correctLumalabasPriced deficiency listA reserve with a number on it
4

Release the holdback less the reserve, and record it

Mga Kontrata

Record the release against the contract for the holdback balance less the valued deficiency reserve, so the ledger shows what was held, what was released, on what date, and against what.

Bakit: The release is the moment a balance and a recomputed percentage stop being the same number, and only writing the release down as a transaction keeps them together. A release nobody recorded is one both sides will later compute differently and each be certain about.

PapasokHoldback balancePriced deficiency reserveLumalabasRelease recorded with its dateA balance that still reconciles
5

Reconcile the final account line by line

Pananalapi

Build the final account from the original contract price, every approved change with its code, holdback released, deficiency deductions and any credits, so that each line points at the transaction that produced it.

Bakit: A final account is agreed when the other side can check it, not when it is delivered. One that can be walked backwards to its transactions settles in a meeting; one that arrives as a total settles in a negotiation, and the negotiation is where the last few percent of the job goes.

PapasokContract price, changes, releases, deductionsLumalabasFinal account, every line traceableA figure that can be walked back
6

Issue the closeout package and keep the file copy

Mga Ulat

Issue the final account together with the certified date, the deficiency list and its status, the holdback release and the warranties, as one package to the client and one record to your own file.

Bakit: The package is what the client's finance department needs before it can pay, and the file copy is what you need when a security claim or a deficiency argument arrives eighteen months later, by which time everyone who did the work has moved to another job.

PapasokFinal account and supporting recordsLumalabasCloseout package issuedA file that survives the team
Mga Module

Mga Module sa Playbook na Ito

6 / 190 na module ng platform

The market this case is written for

Canada

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Higit pa sa Handover at lifecycle

Handover at lifecycle

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 hakbang14 minBukas
Handover at lifecycle

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3 hakbang12 minBukas