Тохиолдлууд / Талбай ба хээрийн ажил
Талбай ба хээрийн ажил

direccion facultativa бичдэг libro de ordenes-ыг хөтлөх

айлчлалыг тэмдэглэх, тушаал бүрийг үнэндээ ямар болохоор нь бичих, тухайн өдрийн гүйцэтгэгчийн өөрийн бүртгэлтэй хослуулах, ажлыг өөрчилдөг зүйлсийг ярианд биш үнэ тогтоосон modificado-д илгээх.

5 алхам14 минЕрөнхий гүйцэтгэгчЗураг төслийн / инженерийн компаниТөслийн / барилгын менежментийн компани

Хэрхэн ажилладаг, алхам алхмаар

Платформ даяар 5 алхам - алхам бүрт юу хийх, яагаад чухал болохыг.

1

Open the visit before you write anything

Талбай дахь хяналт

Record the visit itself: the date, who attended and in which discipline they attended. Every order written that day hangs off it, so the visit is the container rather than the paperwork.

Яагаад: An instruction with no visit behind it is an instruction nobody can place. Which arquitecto tecnico was there, and whether the structural engineer was, decides later whether an order about reinforcement was given by somebody entitled to give it.

ОролтWorks in progressApproved drawings and specificationҮр дүнDated site visit recordAttendance record by discipline
2

Write each order as the kind of thing it is

Талбай дахь хяналт

Enter each observation under its own number and say which kind it is: work confirmed as conforming, a deviation from the project, an acceptance of work about to be covered up, an instruction to do something, or a reasoned refusal. Name the element, the location and the action required.

Яагаад: The type is what decides who has to do what next, and it is the thing free prose loses. A hidden-works acceptance that reads like a general comment is an acceptance nobody can find once the slab is poured, and that is exactly the record everybody wants when the slab is opened again.

ОролтOpen site visit recordWhat was observed on siteҮр дүнNumbered order in the registerRequired action and its status
3

Pair the order with the day it was given

Өдрийн тэмдэглэл

On the same day, record in the diary what was on site: which trades, how many, what plant, the weather and what was actually built. Note the order reference in it so the two records point at each other.

Яагаад: An order to stop and rework is worth whatever the stop cost, and that cost is in the diary rather than in the order. Six months later the two together are evidence; the order on its own is a sentence, and the diary on its own is a page of crew numbers nobody can attribute to anything.

ОролтOrder given that daySite labour, plant and weatherҮр дүнDaily diary recordOrder matched to the day's works
4

Send the ones that change the work to be priced

Өөрчлөлтүүд

An instruction or a deviation that alters the scope becomes a variation, priced from the contract rates where they reach and from a new descompuesto where they do not, with the order reference carried on it.

Яагаад: Orders that change the work and never get priced are the single largest source of unpaid work on a Spanish job, and they are never denied at the time. They are denied at the end, when the only argument left is what somebody meant, and the reference from the order to the priced change is what stops that argument existing.

ОролтInstruction that changes the workContract rates and quantitiesҮр дүнPriced variation raisedOrder linked to the change record
5

Take the open orders to the monthly meeting

Тайлан

Report the orders still open, how long each has been open and who owes the next move, and take that list into the site meeting instead of reading the whole register out.

Яагаад: An order nobody chases is closed by the passage of time, and both sides read that silence in their own favour. A short list of what is still open, tabled once a month, closes most of them without any escalation at all, and the ones that do not close are the real disputes rather than the forgotten ones.

ОролтOrders open and closedҮр дүнReport of open ordersAgenda for the next site meeting
Модулиуд

Энэ тоглолтын модулиуд

Платформын 190 модулиас 4

The market this case is written for

Испани

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • FIEBDC-3 (BC3)
  • LCSP

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Талбай ба хээрийн ажил дахь бусад

Талбай ба хээрийн ажил

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…

4 алхам9 минНээх
Талбай ба хээрийн ажил

Answer an RFI

Turn a question from the working face into a tracked request, drive it to the party who own…

3 алхам9 минНээх
Талбай ба хээрийн ажил

Capture daywork and time and materials

Turn instructed extra work into a claim that gets paid: record the labour, plant and materi…

3 алхам9 минНээх