Kasus / Lapangan dan proyek
Lapangan dan proyek

Menjaga libro de ordenes tempat direccion facultativa menulis

Catat kunjungan, tulis setiap perintah sebagaimana sebenarnya, pasangkan dengan catatan kontraktor sendiri untuk hari itu, dan kirim yang mengubah pekerjaan ke modificado yang diberi harga alih-alih ke percakapan.

5 langkah14 mntKontraktor umumBiro desain / rekayasaBiro manajemen proyek / konstruksi

Cara kerjanya, langkah demi langkah

5 langkah di seluruh platform - apa yang Anda lakukan di setiap langkah dan mengapa itu penting.

1

Open the visit before you write anything

Supervisi Lapangan

Record the visit itself: the date, who attended and in which discipline they attended. Every order written that day hangs off it, so the visit is the container rather than the paperwork.

Tangkapan layar, langkah 1: Open the visit before you write anything (Supervisi Lapangan, Menjaga libro de ordenes tempat direccion facultativa menulis)
Supervisi Lapangan: Open the visit before you write anything

Mengapa: An instruction with no visit behind it is an instruction nobody can place. Which arquitecto tecnico was there, and whether the structural engineer was, decides later whether an order about reinforcement was given by somebody entitled to give it.

MasukanWorks in progressApproved drawings and specificationHasilDated site visit recordAttendance record by discipline
2

Write each order as the kind of thing it is

Supervisi Lapangan

Enter each observation under its own number and say which kind it is: work confirmed as conforming, a deviation from the project, an acceptance of work about to be covered up, an instruction to do something, or a reasoned refusal. Name the element, the location and the action required.

Mengapa: The type is what decides who has to do what next, and it is the thing free prose loses. A hidden-works acceptance that reads like a general comment is an acceptance nobody can find once the slab is poured, and that is exactly the record everybody wants when the slab is opened again.

MasukanOpen site visit recordWhat was observed on siteHasilNumbered order in the registerRequired action and its status
3

Pair the order with the day it was given

Buku Harian Proyek

On the same day, record in the diary what was on site: which trades, how many, what plant, the weather and what was actually built. Note the order reference in it so the two records point at each other.

Tangkapan layar, langkah 3: Pair the order with the day it was given (Buku Harian Proyek, Menjaga libro de ordenes tempat direccion facultativa menulis)
Buku Harian Proyek: Pair the order with the day it was given

Mengapa: An order to stop and rework is worth whatever the stop cost, and that cost is in the diary rather than in the order. Six months later the two together are evidence; the order on its own is a sentence, and the diary on its own is a page of crew numbers nobody can attribute to anything.

MasukanOrder given that daySite labour, plant and weatherHasilDaily diary recordOrder matched to the day's works
4

Send the ones that change the work to be priced

Variasi

An instruction or a deviation that alters the scope becomes a variation, priced from the contract rates where they reach and from a new descompuesto where they do not, with the order reference carried on it.

Tangkapan layar, langkah 4: Send the ones that change the work to be priced (Variasi, Menjaga libro de ordenes tempat direccion facultativa menulis)
Variasi: Send the ones that change the work to be priced

Mengapa: Orders that change the work and never get priced are the single largest source of unpaid work on a Spanish job, and they are never denied at the time. They are denied at the end, when the only argument left is what somebody meant, and the reference from the order to the priced change is what stops that argument existing.

MasukanInstruction that changes the workContract rates and quantitiesHasilPriced variation raisedOrder linked to the change record
5

Take the open orders to the monthly meeting

Laporan

Report the orders still open, how long each has been open and who owes the next move, and take that list into the site meeting instead of reading the whole register out.

Tangkapan layar, langkah 5: Take the open orders to the monthly meeting (Laporan, Menjaga libro de ordenes tempat direccion facultativa menulis)
Laporan: Take the open orders to the monthly meeting

Mengapa: An order nobody chases is closed by the passage of time, and both sides read that silence in their own favour. A short list of what is still open, tabled once a month, closes most of them without any escalation at all, and the ones that do not close are the real disputes rather than the forgotten ones.

MasukanOrders open and closedHasilReport of open ordersAgenda for the next site meeting
Modul

Modul dalam playbook ini

4 / 190 modul platform

The market this case is written for

Spanyol

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • FIEBDC-3 (BC3)
  • LCSP

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Lainnya di Lapangan dan proyek

Lapangan dan proyek

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…