Hold libro de ordenes, som direccion facultativa skriver i

Registrer besøget, skriv hver ordre som det, den faktisk er, par den med entreprenørens egen journal for den dag, og send dem, der ændrer arbejdet, ind i et prissat modificado i stedet for en samtale.

5 trin14 minHovedentreprenørProjekterings- / ingeniørfirmaProjekt- / byggeledelsesfirma

Sådan fungerer det, trin for trin

5 trin gennem platformen - hvad du gør i hvert, og hvorfor det betyder noget.

1

Open the visit before you write anything

Byggepladstilsyn

Record the visit itself: the date, who attended and in which discipline they attended. Every order written that day hangs off it, so the visit is the container rather than the paperwork.

Hvorfor: An instruction with no visit behind it is an instruction nobody can place. Which arquitecto tecnico was there, and whether the structural engineer was, decides later whether an order about reinforcement was given by somebody entitled to give it.

InputWorks in progressApproved drawings and specificationResultatDated site visit recordAttendance record by discipline
2

Write each order as the kind of thing it is

Byggepladstilsyn

Enter each observation under its own number and say which kind it is: work confirmed as conforming, a deviation from the project, an acceptance of work about to be covered up, an instruction to do something, or a reasoned refusal. Name the element, the location and the action required.

Hvorfor: The type is what decides who has to do what next, and it is the thing free prose loses. A hidden-works acceptance that reads like a general comment is an acceptance nobody can find once the slab is poured, and that is exactly the record everybody wants when the slab is opened again.

InputOpen site visit recordWhat was observed on siteResultatNumbered order in the registerRequired action and its status
3

Pair the order with the day it was given

Byggedagbog

On the same day, record in the diary what was on site: which trades, how many, what plant, the weather and what was actually built. Note the order reference in it so the two records point at each other.

Hvorfor: An order to stop and rework is worth whatever the stop cost, and that cost is in the diary rather than in the order. Six months later the two together are evidence; the order on its own is a sentence, and the diary on its own is a page of crew numbers nobody can attribute to anything.

InputOrder given that daySite labour, plant and weatherResultatDaily diary recordOrder matched to the day's works
4

Send the ones that change the work to be priced

Ekstraarbejder

An instruction or a deviation that alters the scope becomes a variation, priced from the contract rates where they reach and from a new descompuesto where they do not, with the order reference carried on it.

Hvorfor: Orders that change the work and never get priced are the single largest source of unpaid work on a Spanish job, and they are never denied at the time. They are denied at the end, when the only argument left is what somebody meant, and the reference from the order to the priced change is what stops that argument existing.

InputInstruction that changes the workContract rates and quantitiesResultatPriced variation raisedOrder linked to the change record
5

Take the open orders to the monthly meeting

Rapporter

Report the orders still open, how long each has been open and who owes the next move, and take that list into the site meeting instead of reading the whole register out.

Hvorfor: An order nobody chases is closed by the passage of time, and both sides read that silence in their own favour. A short list of what is still open, tabled once a month, closes most of them without any escalation at all, and the ones that do not close are the real disputes rather than the forgotten ones.

InputOrders open and closedResultatReport of open ordersAgenda for the next site meeting
Moduler

Moduler i denne playbook

4 / 190 platformmoduler

The market this case is written for

Spanien

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • FIEBDC-3 (BC3)
  • LCSP

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Mere inden for Byggeplads og felt

Byggeplads og felt

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…