Казуси / Предаване и жизнен цикъл
Предаване и жизнен цикъл

Приключете строежа и предайте libro del edificio

Осигурете подпис на certificado final de obra, вземете acta de recepcion със записани reservas, стартирайте трите гаранционни периода от тази дата, съставете libro del edificio и предайте на собственика инструкции, по които той реално може да управлява сградата.

5 стъпки20 минГлавен изпълнителИнвеститор / възложителСобственик / оператор (FM)

Как работи, стъпка по стъпка

5 стъпки през платформата - какво правите на всяка и защо е важно.

1

Get the certificado final de obra signed

Електронни подписи

Send the certificado final de obra for signature by both members of the direccion facultativa, the one who directed the works and the one who directed their execution. Keep the record of who signed and when.

Защо: Nothing downstream can start without it: not the recepcion, not the licencia de primera ocupacion, not the release of retention. It is also the point where an outstanding item still gets fixed quickly, because everybody wants the same signature.

ВходCompleted worksDireccion facultativa, both rolesРезултатSigned completion certificateSignature trail with dates
2

Take the recepcion with the reservas written into it

Приключване

Work the closeout checklist to the point where the package is genuinely complete, then record the acta de recepcion with its date and any reservas set out item by item, along with the period allowed to clear them.

Защо: A recepcion taken with a vague reserva about finishes is a recepcion where every later disagreement is about what was meant. Written item by item, the reserva names what is outstanding and the rest of the building is received, which is what both sides actually want.

ВходSigned completion certificateOutstanding items listРезултатActa de recepcion with its dateReservas written down, not agreed
3

Start the guarantee periods from that date

Гаранции и отговорност за дефекти

Enter the guarantee periods by hand against the recepcion date: twelve months for defects in the finishes, thirty-six for those affecting habitability, one hundred and twenty for those touching structure. The register ships no Spanish regime, so leave the regime unset and let the period you entered stand as entered.

Защо: The three periods are the reason a defect reported in year four is a different conversation from the same defect in year two, and nobody reconstructs that from memory. Entered as dates, the register answers it; left to be worked out later, it becomes an argument between people who each remember a different rule.

ВходActa de recepcion dateElements and work packagesРезултатWarranty register entriesGuarantee end dates on record
4

Assemble the libro del edificio

Документи

Gather what the libro has to carry: the project as built, the acta de recepcion, the list of the parties who took part with their details, the certificates and guarantees, and the instructions for use and maintenance. File it as one indexed set rather than as a folder somebody has to interpret.

Защо: The libro is read by people who were not there, years later, usually because something has failed. An index that says what is inside is what turns it from an archive into a document, and the party list is what tells the community who to write to when the ten-year period still has time on it.

ВходAs-built drawings and project fileCertificates and guaranteesРезултатLibro del edificio document packIndex of what is inside it
5

Hand over instructions the owner can run the building on

Регистър на активи

Load the plant and equipment into the asset register with its location, its guarantee end date and the maintenance the instructions require, so the use and maintenance section of the libro becomes a list of things due rather than a chapter.

Защо: A guarantee is lost far more often through maintenance nobody did than through a defect nobody reported. The register is what makes the difference visible in the first year, while the periods still have most of their time left and the contractor is still answering the phone.

ВходLibro del edificio document packInstalled plant and equipmentРезултатAsset register the owner can useMaintenance schedule per asset
Модули

Модули в този наръчник

5 / 190 модула на платформата

The market this case is written for

Испания

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • FIEBDC-3 (BC3)
  • LCSP

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Още в Предаване и жизнен цикъл

Предаване и жизнен цикъл

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 стъпки14 минОтвори
Предаване и жизнен цикъл

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3 стъпки12 минОтвори
Предаване и жизнен цикъл

Run a handover acceptance inspection

Walk the finished works with the client, record what passes and what does not against the a…

3 стъпки11 минОтвори