Raise a subcontract order from the award

Turn a winning bid into a live subcontract order: confirm the agreed scope and rates, raise the order, attach the programme and payment terms, and issue the contract for signature.

4 خطوة11 دقيقةمقاول عاممدير مشروع / مدير إنشاءاستشاري تكاليف / مساح كميات

كيف يعمل، خطوة بخطوة

4 خطوات عبر المنصة - ما تفعله في كل منها ولماذا يهم.

1

Confirm the award

إدارة العطاءات

Open the awarded bid and confirm the final scope, rates and any post-tender agreements, so the order is raised against the deal that was actually struck.

لماذا: Post-tender negotiations change numbers that the original bid still shows. Confirming the settled position first is what stops the wrong figure being written into the contract.

المدخلاتAwarded bidAgreed scopeالمخرجاتConfirmed deal
2

Raise the order

المشتريات

Raise the purchase or subcontract order straight from the award, carrying the priced scope so the committed value ties back to the bill and the budget.

لماذا: An order built from the award keeps the commitment stitched to the estimate. Rekeying it by hand is where a rate gets transposed and a package quietly overspends.

المدخلاتConfirmed dealالمخرجاتSubcontract order
3

Attach programme and terms

دليل المقاولين الفرعيين

Attach the package programme dates, the payment terms, retention and the key obligations to the subcontractor record, so the deal is complete rather than just a price.

لماذا: A price with no dates and no terms is where disputes start. Pinning the programme and the payment mechanism to the order now saves the argument later.

المدخلاتSubcontract orderPackage programmeالمخرجاتSubcontractor record
4

Issue for signature

العقود

Issue the subcontract for signature and file the executed copy against the project, so the commitment is contractually live before the trade starts on site.

لماذا: A subcontractor working without a signed order is a risk to both sides. Getting the contract executed before mobilisation is the discipline that keeps the package governable.

المدخلاتComplete orderالمخرجاتExecuted contract