Raise a subcontract order from the award

Turn a winning bid into a live subcontract order: confirm the agreed scope and rates, raise the order, attach the programme and payment terms, and issue the contract for signature.

4 steps11 minGeneral contractorProject / construction management firmCost consultancy / QS practice

How it works, step by step

4 steps across the platform - what you do at each one, and why it matters.

1

Confirm the award

Bid Management

Open the awarded bid and confirm the final scope, rates and any post-tender agreements, so the order is raised against the deal that was actually struck.

Why: Post-tender negotiations change numbers that the original bid still shows. Confirming the settled position first is what stops the wrong figure being written into the contract.

InAwarded bidAgreed scopeOutConfirmed deal
2

Raise the order

Procurement

Raise the purchase or subcontract order straight from the award, carrying the priced scope so the committed value ties back to the bill and the budget.

Why: An order built from the award keeps the commitment stitched to the estimate. Rekeying it by hand is where a rate gets transposed and a package quietly overspends.

InConfirmed dealOutSubcontract order
3

Attach programme and terms

Subcontractors

Attach the package programme dates, the payment terms, retention and the key obligations to the subcontractor record, so the deal is complete rather than just a price.

Why: A price with no dates and no terms is where disputes start. Pinning the programme and the payment mechanism to the order now saves the argument later.

InSubcontract orderPackage programmeOutSubcontractor record
4

Issue for signature

Contracts

Issue the subcontract for signature and file the executed copy against the project, so the commitment is contractually live before the trade starts on site.

Contracts screen in OpenConstructionERP: issue for signature

Why: A subcontractor working without a signed order is a risk to both sides. Getting the contract executed before mobilisation is the discipline that keeps the package governable.

InComplete orderOutExecuted contract
Modules

Modules in this playbook

4 / 190 platform modules

More in Tendering & procurement

Tendering & procurement

Run a tender from a BOQ

Take a priced bill of quantities out to market: package it, invite the subcontractors, leve…

5 steps12 minOpen
Tendering & procurement

Procure materials from the BOQ

Buy the quantities you already priced: raise a requisition off the bill, place the order wi…

4 steps10 minOpen
Tendering & procurement

Compare bids and award

Take a folder of returned tenders that never quite match, strip them back to the same scope…

3 steps12 minOpen