ケース / 入札と調達
入札と調達

Raise a subcontract order from the award

Turn a winning bid into a live subcontract order: confirm the agreed scope and rates, raise the order, attach the programme and payment terms, and issue the contract for signature.

4ステップ11 分総合建設会社プロジェクト / 施工管理者コストコンサルタント / 積算士

仕組みをステップごとに

プラットフォーム全体で4ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Confirm the award

入札管理

Open the awarded bid and confirm the final scope, rates and any post-tender agreements, so the order is raised against the deal that was actually struck.

理由: Post-tender negotiations change numbers that the original bid still shows. Confirming the settled position first is what stops the wrong figure being written into the contract.

入力Awarded bidAgreed scope出力Confirmed deal
2

Raise the order

調達

Raise the purchase or subcontract order straight from the award, carrying the priced scope so the committed value ties back to the bill and the budget.

理由: An order built from the award keeps the commitment stitched to the estimate. Rekeying it by hand is where a rate gets transposed and a package quietly overspends.

入力Confirmed deal出力Subcontract order
3

Attach programme and terms

下請業者一覧

Attach the package programme dates, the payment terms, retention and the key obligations to the subcontractor record, so the deal is complete rather than just a price.

理由: A price with no dates and no terms is where disputes start. Pinning the programme and the payment mechanism to the order now saves the argument later.

入力Subcontract orderPackage programme出力Subcontractor record
4

Issue for signature

契約

Issue the subcontract for signature and file the executed copy against the project, so the commitment is contractually live before the trade starts on site.

理由: A subcontractor working without a signed order is a risk to both sides. Getting the contract executed before mobilisation is the discipline that keeps the package governable.

入力Complete order出力Executed contract