Build a milestone payment schedule

Tie payment milestones to real programme events, value each one so the schedule sums back to the contract, agree it with the client and read the whole thing back as a cash flow.

4단계10 분종합건설사원가 컨설턴트 / 적산사시행사 / 발주처

작동 방식, 단계별로

플랫폼 전반에 걸친 4단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Mark the payment milestones

4D 공정표

Pick the programme events that clearly prove progress - foundations complete, watertight, services on, handover - and mark each as a payment milestone.

이유: Payment on a verifiable event removes the monthly haggle over percentage complete. Choosing unambiguous milestones is what keeps the cash flowing without a dispute each cycle.

입력Baseline programmeContract terms결과Payment milestones
2

Value each milestone

계약

Attach a value to each milestone from the priced work it represents, and check the milestones sum exactly to the contract with nothing lost or double counted.

이유: Front-loaded milestones flatter the contractor and worry the client; back-loaded ones do the reverse. Valuing each one off the real work keeps the schedule fair and fundable.

입력Payment milestonesContract sum결과Valued schedule
3

Agree it with the client

계약

Agree the milestone schedule with the client as the contractual basis for drawdown, so both sides sign up to what triggers each payment before work starts.

이유: A schedule agreed up front is a schedule that pays on time. Settling the triggers before the money is due is what stops each milestone becoming a fresh negotiation.

입력Valued schedule결과Agreed schedule
4

Read it as a cash flow

재무

View the milestone payments across the programme as a cash flow forecast, so the client can plan funding and you can see when the money actually arrives.

이유: Milestones set the timing of cash, and cash timing is what keeps a job solvent. Seeing the curve early lets both sides fix a lumpy month before it becomes a funding crunch.

입력Agreed schedule결과Cash flow forecast