Build a milestone payment schedule
Tie payment milestones to real programme events, value each one so the schedule sums back to the contract, agree it with the client and read the whole thing back as a cash flow.
Cách hoạt động, từng bước một
4 bước xuyên suốt nền tảng - bạn làm gì ở mỗi bước và vì sao điều đó quan trọng.
Mark the payment milestones
Tiến độ 4DPick the programme events that clearly prove progress - foundations complete, watertight, services on, handover - and mark each as a payment milestone.
Tại sao: Payment on a verifiable event removes the monthly haggle over percentage complete. Choosing unambiguous milestones is what keeps the cash flowing without a dispute each cycle.
Value each milestone
Hợp đồngAttach a value to each milestone from the priced work it represents, and check the milestones sum exactly to the contract with nothing lost or double counted.
Tại sao: Front-loaded milestones flatter the contractor and worry the client; back-loaded ones do the reverse. Valuing each one off the real work keeps the schedule fair and fundable.
Agree it with the client
Hợp đồngAgree the milestone schedule with the client as the contractual basis for drawdown, so both sides sign up to what triggers each payment before work starts.
Tại sao: A schedule agreed up front is a schedule that pays on time. Settling the triggers before the money is due is what stops each milestone becoming a fresh negotiation.
Read it as a cash flow
Tài chínhView the milestone payments across the programme as a cash flow forecast, so the client can plan funding and you can see when the money actually arrives.
Tại sao: Milestones set the timing of cash, and cash timing is what keeps a job solvent. Seeing the curve early lets both sides fix a lumpy month before it becomes a funding crunch.