Отворете демото
Казуси / Планиране и контрол
Планиране и контрол

Import a programme and set the baseline

Bring an external programme in from an exchange file, check the calendars and links survived the trip, set the accepted programme as the baseline and publish it so progress is measured against something fixed.

4 стъпки10 минГлавен изпълнителРъководител на проект / строителствоСпециализиран подизпълнител

Как работи, стъпка по стъпка

4 стъпки през платформата - какво правите на всяка и защо е важно.

1

Import the programme

Разширен график

Import the programme from its exchange file so the activities, durations, logic links and WBS come across without being rekeyed line by line.

Защо: Retyping a programme of a few hundred activities loses the logic that makes it a programme. Importing keeps the network intact so the critical path is real, not redrawn from memory.

ВходProgramme exchange fileРезултатImported activities
2

Check what came across

Разширен график

Confirm the calendars, the logic links and the WBS survived the import, and that the completion date matches the source, before anyone trusts a date on it.

Защо: Exchange files drop constraints and remap calendars silently. Catching a shifted completion date now is far cheaper than discovering the imported programme was wrong three months in.

ВходImported activitiesCalendars and linksРезултатChecked programme
3

Set the baseline

4D график

Freeze the agreed programme as the baseline, the fixed reference the job will be measured against for the rest of its life.

Защо: The baseline is the promise. Without a frozen one there is nothing to compare progress to, and every slippage argument becomes a matter of opinion instead of a matter of record.

ВходChecked programmeРезултатFixed baseline
4

Publish it for tracking

Напредък

Publish the baseline so the team records progress against it and the planned-versus-actual picture builds from day one.

Защо: A baseline nobody tracks against is a wall decoration. Publishing it turns the programme into a live control that warns you early rather than a document reviewed after the fact.

ВходFixed baselineРезултатProgress tracking on

Още в Планиране и контрол